7.1.5 Restore to normal operation after “total off”
View of the panel after pressing the button “total off”.
•All Contacts are open;
•Rectifier, Inverter and
1.Reset “total off” by pressing and holding the “total off” button and then the “inverter on” ( I ) key simultaneously until Load is supplied from Bypass and the Rectifier starts.
•Output connects to Bypass Utility.
•Rectifier starts with blinking LED.
•At the end of
•The LCD screen shows: “LOAD ON BYPASS”.
•Press mute, to reset alarm and buzzer.
2.Connect the Battery to the UPS by closing the Battery Switch or Fuses, in case of External Battery.
3.Press “inverter on” ( I ) key.
•
•At the end of
•Automatic transfer from Bypass to Inverter.
•UPS output LED indicates Load on Inverter.
The LCD must display on the main screen the status “LOAD ON INVERTER”.
End of procedure