7.3.2 Maintenance system shutdown (Load supplied from Q2 on all Units)
Initial status: Load supplied from all Inverters.
| First operated unit | All other units of the system |
|
| |
1. | Press “inverter off” ( O ) key on all Units, and hold until the LED inside the Inverter | |
| symbol turns OFF. |
|
| At no redundancy, the system will transfer to Utility supply. | |
| First operated unit | All other units of the system |
|
|
|
2. | Close Q2 (Pos. I) on all Units. |
|
| Load is now supplied from Utility in parallel from Bypass and Manual Bypass Q2 of all Units. | |
| First operated unit | All other units of the system |
|
| |
3. | Open Q1 (Pos. O) and then press “total off” button on all Units. | |
| The Bypass of all Units will disconnect and all Rectifiers are shutdown. | |
| First operated unit | All other units of the system |
|
| |
4. | Disconnect the Battery, in case of External Battery, from all Units. | |
| • Wait 5 minutes for |
|
| First operated unit | All other units of the system |
|
|
|
| End of procedure |
|