Introduction to STS2/PDU Operations

8.1.2Reliability and Agency Requirements

The STS2/PDU is designed for high reliability and high availability with a critical bus Mean Time Between Failure (MTBF) exceeding 1,000,000 hours.

The STS2/PDU and all its options are designed, tested and certified, where applicable, to meet agency requirements as follows:

UL 891: Standard for Switchboard, for UL and ULc listing

UL 1008: Standard for Automatic Transfer Switches

UL 67: Standard for Panelboard

UL 1561: Standard for Dry Transformers

UL 1459: Telephone equipment (Modem)

NEC

FCC Part 15 EMI emission limits for Class A computing devices.

The STS2/PDU uses conservatively rated components, minimizing the need to go to maintenance bypass. All normal maintenance and repair work can be done through the front panel of the unit. This access makes repairs and maintenance easier.

Gating and control logic are partitioned so that failure of one source’s gating or sensing logic does not prevent the switch from transferring to the other source.

All control and logic components are mounted separate from the power components. The STS2/PDU is designed to minimize the exposure of hazardous voltages to allow safe servicing of the unit while the load is energized.

All electrical components requiring normal maintenance are replaceable without de-energizing the load, as long as one source is available. Solid-state switching devices are packaged to allow safe repair of those devices without having to de-energize the load. All non-automatic switches or circuit breakers are the plug-in or draw-out type to allow replacement without de-energizing the load. All other com- ponents, including transformers, power cables and connections, circuit breaker bases, etc., are replaceable from the front, rear or top of the unit—however, this requires all power to be removed from the unit for safety. All solid-state power switching devices are rated to prevent hazardous device failure in power systems with available fault currents up to the defined limits, as listed in 14.1.6 - Electrical Requirements.

8.1.3Factory Backup and Service Assistance

Because improper installation can cause a system to fail, a Liebert Global Services or a factory trained service technician should thoroughly inspect the unit to ensure it is properly installed and its operating parameters are properly configured.

Once the STS2/PDU is properly installed, you, as the on-site operator, can easily monitor the unit’s operation utilizing the touch screen.

In the United States, if you need assistance or have questions, call 1-800-LIEBERT (1-800-543-2378). Outside the 48 contiguous United States, contact Liebert Global Services, if available in your area.

For international areas not covered by Liebert Global Services, the Liebert authorized distributor can provide technical support.

8.2Modes of Operation

8.2.1Normal (Preferred Source)

Under normal operating conditions, the STS2/PDU routes power from the preferred input source to the output load. The unit monitors the voltage current and phase of each source to ensure that both are operating within set tolerances and that the alternate source is available, should a transfer be required.

70