Locating The STS2/PDU

3.0LOCATING THE STS2/PDU

This section provides instructions for leveling the STS2/PDU and anchoring the unit to the floor, should that be required.

3.1Anchoring the Unit to the Floor

The STS2/PDU can be anchored to the concrete floor to ensure stability for the unit in the event of seismic activity.

3.2Leveling of the 250A Only STS2/PDU Without Anchoring

The 250A Static Transfer Switch 2 Power Distribution Unit is furnished with casters and leveling feet. After final positioning of the unit, adjust the leveling feet located in each corner of the frame base to level and stabilize the unit.

For leveling feet details, see Figures 7 through 11.