A-10

INSTALLATION

A-10

 

 

 

 

STEP BY STEP INSTALLATION CHECKLIST

 

TANDEM ARC SYSTEM CHECKLIST (PF-10A CONTROLLED, 1 POWER SOURCE PER ARC)

(as shown in the Connection Diagram "Typical Tandem Arc System”)

Place Power Waves in suitable operating location.

Mount PF10A Controllers.

Install PF10S Wire Drives and other accessories in their operating location.

Mount Power Wave System Interface.

Connect K1785-xx Wire Feeder Control Cable (14 pin) between each Power Wave and Wire Drive.(1)

Connect K1543-xx ArcLink Control Cables (5 pin) from Power Wave #1 to the System Interface input, and from the System Interface output to the PF10A Controller for ARC #1.(1)

Connect K1543-xx ArcLink Control Cable (5 pin) between Power Wave #2 and the PF10A Controller for ARC #2.(1)

Connect K1795-xx System Control Cables (22 pin) between each Power Wave and the System Interface. (2)

Configure / Install sense leads.

Connect / Install welding cables per recommended "Output Cable Guidelines."

Open all Power Wave front panels and configure DIP switch settings per "Internal Controls" section.

Connect input power to Power Waves per recommended guidelines.

Turn on Power Waves, and verify all system Status Lights are solid green.

NOTES:

(1)ArcLink and Wire Feeder control cable connections are only required at the Master power source of each arc grouping. For additional information see the "Extra Capacity Parallel Connection Checklist."

(2)The "ARC" (formerly "PHASE") connections from the System Interface are only required for the Master power source of each arc grouping. For additional information see the "Extra Capacity Parallel Connection Checklist."

POWER WAVE® AC/DC 1000

Page 20
Image 20
Lincoln Electric 11226, 11124 manual Step by Step Installation Checklist