CVX 600 Hardware Installation Guide

Mounting the CVX 600 in a Rack

Space Requirements

The following table lists the PTE 2000 racks and dimensions.

Rack Type

Part Number

Width in

Depth in

Height in

Inches (mm)

Inches (mm

Inches (mm)

 

 

 

 

 

 

 

NEBS-compliant rack

NTRU0134

23.6 (600)

23.6 (600)

83.66 (2125)

 

 

 

 

 

ETSI-compliant rack

NTRU0234

23.6 (600)

23.6 (600)

86.6 (2200)

 

 

 

 

 

Flooring Requirements

You must anchor the PTE 2000 rack to the equipment-room floor. The flooring can be one of the following types:

Raised floor tiles, ideally with a clearance of 18 in. (45.5 cm), and a subfloor cable management system

Bare concrete floor

Depth for Drilling

If you plan to install the PTE 2000 floor anchors on a bare concrete floor, you must drill to the following depths:

2 in. (51 mm) for the 3/8 in. anchor (for zone 2 earthquake compliance, NTRU0323/NTRU0326)

4 in. (103 mm) for the M12 anchor (for zone 4 earthquake compliance, NTRU0324/NTRU0328)

Warning: Before you begin to drill, make sure you are familiar with the building construction. If you plan to drill holes in a below-ground structure, make sure that you do not drill through the concrete into the vapor barrier. If you do, groundwater may seep through the anchor hole.