Chapter 2 - Hardware Installation
Unpacking and Positioning the MGC+100
To unpack and position the MGC+100:
1.When you receive your MGC+100, inspect the equipment for damage and verify that the components match the packing slip. If you did not receive a component or if there is damage to the system, notify your service representative immediately.
Wood Packing Case
Carrying Strap
Lock in Closed Position
Lock in Open Position
Figure 2-1: MGC+100 package
2.Place the MGC+100 unit on a stable flat surface in a location that meets the MGC+ environment requirements, which are:
—Operating temperature:
—Humidity:
—Altitude: Up to 3,000m (10,000ft)
—ESD: +8 kV