4 Inch Concentric Termination Installation

 

 

 

INTAKE AIR CONNECTION

INTAKE AIR PIPE

 

 

 

3 INCH PVC

 

VENT PIPE

 

 

 

 

3” x 3” x 4”

 

 

 

 

 

Y FITTING

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

When installing 4 inch intake air and vent pipe - connect the piping to the concentric termination using field supplied 4" x 3" reducer couplings and short sections of 3 inch pipe (18 inches or less) pipe. Cement all fittings and pipe in place.

9.Return to Direct Vent Installation on page 25 to complete the installation of the intake air and vent piping between the concentric termination and the water heater.

VENT CONNECTION - 3 INCH PVC

VENT CAP

VENT PIPE IS 2 1/2 INCH SDR-26 PIPE SUPPLIED LENGTH 37 INCHES (94 cm)

MAXIMUM ALLOWABLE LENGTH 73 INCHES (185 cm) MINIMUM ALLOWABLE LENGTH 25 INCHES (64 cm)

INTAKE AIR PIPE IS 4 INCH SDR-26 PIPE SUPPLIED LENGTH 24 INCHES (60 cm)

MAXIMUM ALLOWABLE LENGTH 60 INCHES (152 cm) MINIMUM ALLOWABLE LENGTH 12 INCHES (30 cm)

INTAKE AIR PIPE

Y FITTING ASSEMBLY

VENT CAP

VENT PIPE ASSEMBLY

COMBUSTION

AIR

ROOF FLASHING (field supplied)

VENT

MAINTAIN 12” (30 cm) 18” (45 cm) FOR CANADA MINIMUM CLEARANCE ABOVE HIGHEST ANTICIPATED SNOW LEVEL. MAXIMUM OF 24” (60 cm) ABOVE ROOF.

STRAP (field supplied)

NOTE: SECURING STRAP MUST BE FIELD INSTALLED TO PREVENT MOVEMENT OF TERMINATION KIT

4 INCH CONCENTRIC TERMINATION KIT

FOUR PIECE KIT - FIELD ASSEMBLY REQUIRED

Figure 29

Assemble and install the 4 inch concentric termination. Refer to Figure 29, Figure 30 and Figure 31 for these instructions:

1.

Cement the Y fitting to the larger diameter intake air pipe.

2.

Slide the intake air pipe and Y fitting assembly from inside the

VENT

INTAKE

PIPE

AIR PIPE

4 INCH CONCENTRIC TERMINATION

VERTICAL INSTALLATION

Figure 30

 

building through the hole cut for the termination in the roof

 

or sidewall. Ensure no foreign materials such as insulation

 

accumulate inside the assembly.

3.

Secure the intake air Y fitting assembly using field supplied

 

metal strapping or equivalent support materials.

4.

On installations installed through the roof slide a field

 

supplied plumbing boot or roof flashing over the intake air Y

 

fitting assembly and secure it to the roof.

5.

Seal around the plumbing boot or roof flashing.

6.

Cement the vent cap onto the vent pipe. Alternately a field-

 

supplied stainless steel screw may be used to secure the 2

 

components together when field disassembly is desired for

 

cleaning. A pilot hole must be drilled for the screw to prevent

 

damage/cracking of the vent cap and/or vent pipe.

NOTE: SECURING STRAP MUST BE FIELD INSTALLED TO PREVENT MOVEMENT OF TERMINATION KIT IN SIDEWALL.

VENT

STRAP

PIPE

(field supplied)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

COMBUSTION

AIR

VENT

1 INCH

MAXIMUM

7.

Install the vent cap/vent pipe assembly into the intake air Y

 

fitting assembly, Ensure small diameter vent pipe is cemented

 

and bottomed in the Y fitting.

8.

When installing 3 inch intake air and vent piping connect

 

and cement the pipe directly to the concentric termination.

INTAKE

AIR PIPE

4 INCH CONCENTRIC TERMINATION

SIDEWALL INSTALLATION

Figure 31

31

Page 31
Image 31
State Industries SUF-100-250, SUF-60-120 Inch Concentric Termination Installation, Inch Concentric Termination KIT