Installation
Functional Tests
Functional Tests
Equipment Required
These functional test procedures include
•Digital voltmeter (DVM) rated better than 0.5% accuracy.
•DC shunt 1 mV/A (±0.25%) with connecting wire. The recommended current ratings for the DC shunt and the wire must be at least 10% more than the output current of the power supply.
Power-on Check
1.Ensure that the AC power switch is in the OFF position.
2.Ensure that the output sense lines are connected in the default configuration. (The local sense lines are connected between terminals 1 and 2 and between terminals 4 and 5 on the J10 sense connector as shown on the rear panel diagram in Figure .)
3.Turn the voltage and current controls fully
4.Connect the unit to an AC outlet.
5.Turn the front panel AC power switch to ON.
After a short,
Voltage Mode
Operation
Check
1.Ensure the voltage and current controls on the front panel are turned fully
2.Connect a DVM to the output terminals on the rear panel, observing correct polarity.
3.Turn the current control a
4.Compare the DVM reading with the front panel voltmeter reading to verify the accuracy of the internal voltmeter. Both readings should be the same. The minimum control range is from zero to the maximum rated output for the power supply model. The voltage mode LED turns on.
5.Turn the front panel AC power switch to OFF.
Release 2.1 | 43 |