Lincoln Electric SVM208-A service manual GENERATOR/WELDER Maintenance, Screws Brushes

Page 42

D-6

MAINTENANCE

D-6

 

Return to Master TOC

Return to Master TOC

GENERATOR/WELDER MAINTENANCE

STORAGE: Store the Bulldog® 140 in clean, dry, protected areas.

CLEANING: Blow out the generator and controls periodically with low pressure air. Do this at least once a week in particularly dirty areas.

BRUSH REMOVAL AND REPLACEMENT: See Figure D.6. It’s normal for the brushes and slip rings to wear and darken slightly. Inspect the brushes when a general overhaul is necessary. Remove the brushes and clean the slip rings with fine grit emery paper.

CAUTION

Do not attempt to polish slip rings while engine is running.

---------------------------------------------------------------------

To reinstall the brushes (Item 5), press them upward and slide a cable tie (Item 6) through the brush hold- er tabs as shown in figure D.6. Install the brush hold- er (Item 1) into the bearing end bracket (Item 3) and secure with the screws (Item 4) previously removed. Remove the cable tie and the brushes will seat onto the slip rings and replace bearing bracket end cover (Item 2).

RECEPTACLES: Keep the electrical receptacles in good condition. Remove any dirt, oil, or other debris from their surfaces and holes.

CABLE CONNECTIONS: Check the welding cable connections at the weld output terminals often. Be sure that the connections are always tight.

NOTE: Lincoln offers a rotor removal kit for any ser- vice which requires removal of the rotor from the engine. See the ACCESSORIES section for further details.

Removal of engine/generator assembly from the cra- dle can be achieved as follows:

Remove the two 5/16-18 hex head cap screws from the engine block via the access hole located in the cradle cross support channel. Leave all other engine mountings intact.

Remove the two hex nuts from the isolator thread- ed posts at the stator support bracket located oppo- site the engine. Leave all other stator mountings intact.

With a jib hoist or crane, lift the unit upward and remove loose cradle from engine/generator assem- bly.

Return to Section TOC

Return to Section TOC

Return to Section TOC

Return to Section TOC

Return to Master TOC

Return to Master TOC

FIGURE D.6. – BRUSH REMOVAL AND REPLACEMENT

1 3

6 2

4 5

1.BRUSH, BRUSH HOLDER ASSEMBLY

2.BEARING BRACKET END COVER

3.ENGINE END BRACKET

4.(2) SCREWS

5.(2) BRUSHES

6.CABLE TIE

BULLDOG® 140

Image 42
Contents Bulldog Safety California Proposition 65 WarningsElectric Shock can kill ARC Rays can burn Can be dangerousWelding and Cutting Sparks can cause fire or explosion Cylinder may explode if damagedIii Précautions DE Sûreté Sûreté Pour Soudage a L’ArcSafety Methods of Reducing Emissions Mains Supply Master Table of Contents for ALL Sections Table of Contents Installation Section Installation Technical Specifications Bulldog 140 K2708-1Storing Safety PrecautionsLocation and Ventilation Engine Exhaust can killTilting PRE-OPERATION Engine ServiceStacking OILElectrical Output CONNEC- Tions Welding Cable ConnectionsTable A.1 Recommended Welding Cable Size and Length Electrical Connections Auxiliary Power ReceptaclesCable Installation Plugs and HAND-HELD EquipmentPremises Wiring Circuit BreakersAtion. do not RUN These BulldogTable of Contents Operation Section Operation Limitations WELDER/GENERATOR ControlsOutput Panel Controls Engine Operation Gasoline Engine ControlsBefore Starting the Engine Starting the EngineGenerator Operation Table B.1 Generator Power Applications Welding Operation Control Function / OperationStick Welding Material Thickness Electrode Type Size SettingWelding Guidelines Learning To Stick WeldWhat Happens in the Arc? Correct Welding Position Side viewDo the following PracticeUse the following Butt JointsFillet Joints PenetrationVertical-Up Welding Vertical-Down WeldingWelding Sheet Metal How to Hardface the Sharp Edge Metal to Ground WearOverhead Welding Hardfacing To Reduce WearWelding Cast Iron Cast Iron Plate PreparationHigh-Speed Group AWS E6013 Low Hydrogen Group AWS E7018Out-of-Position Group AWS E6011 Bulldog Table of Contents Accessories Section Accessories OPTIONS/ACCESSORIESLincoln Electric Accessories Table of Contents Maintenance Section Maintenance Routine and Periodic Maintenance Engine MaintenanceLocation Engine Adjustments Return to Section TOC To Section TOCTable D.1 Engine Maintenance Parts Spark Plug ServiceOperational Clearance GENERATOR/WELDER Maintenance Screws BrushesFigure D.7. Major Component Locations Bulldog 1TABLE of CONTENTS-THEORY of Operation Section E-1 Theory of Operation ENGINE, EXCITATION, Rotor StatorRotor Field Feedback Auxiliary Power Figure E.3 Rotor Field Feedback and Auxiliary PowerAuxiliary Power Overcurrent Protection Weld Winding and Reactor1TABLE of Contents Troubleshooting and Repair F-1 Troubleshooting and Repair HOW to USE Troubleshooting GuidePC Board Troubleshooting Procedures Output Problems Electric Authorized Field Ser vice Facility Perform the Rotor Voltage TestProblems Symptoms Troubleshooting and Repair Perform Field Diode Test Engine Problems Troubleshooting and Repair Engine Throttle Adjustment Test Bulldog Rotor Voltage Test Test DescriptionMaterials Needed Procedure Rotor Voltage TestLead 200A Connection Ground Stud Field Diode Bridge Test Field Diode Bridge Test + ~Rotor Flashing Circuit Test Rotor Flashing Circuit Test Figure F.3 Brush Holder Leads 201- and 202B +Moving Parts can injure Bulldog Rotor Resistance Test Rotor Resistance Test Cable TIE Brushes Figure F.6 Brushes Retained with Cable TIEBulldog Engine Throttle Adjustment Test ROBIN/SUBARU Engine Strobe-tach Method Engine Throttle Adjustment TestROBIN/SUBARU Engine Frequency Counter MethodHigh Speed Stop Screw Scope Settings Normal Open Circuit Voltage Waveform 115VAC Supply High Idle no LoadTypical Weld Output Waveform Machine LoadedMachine Loaded to 125 Amps AT 23 VAC Brush Removal and Replacement Brush Removal and Replacement Cable TIE BrushesReturn to Section Return to Section TOC Bulldog Rheostat Removal and Replacement Rheostat Removal and Replacement Figure F.11 Rheostat RemovalCapacitor AND/OR Diode Bridge Removal and Replacement Removal and Replacement Procedure Capacitor Removal and ReplacementCapacitor AND/OR Diode Bridge Procedure Field Diode Bridge Removal and Replacement Figure F.13 Field Diode Bridge LocationBulldog STATOR/ROTOR Removal and Replacement InstructionsSTATOR/ROTOR Removal and Replacement GeneratorengineFigure F.15 Generator Components Troubleshooting and Repair Stator Removal Procedure Figure F.16 Output Lead Location TIE Wrap TerminalsThru Bolts Support NutsRotor Removal Procedure Reassembly ProcedureFigure F.19 Checking ROTOR-STATOR AIR GAP Engine Output Auxiliary Power Receptacle OUTPUT1Retest After Repair WELDER/GENERATOR OUTPUT1Bulldog Table of Contents Diagram Section Wiring Diagram Bulldog S28101