Initial Start-up (No Load)

Before operating the home generator or placing it into service, inspect the entire installation carefully.

Then begin testing the system without any electrical loads connected, as follows:

1.Set generator’s main circuit breaker to its ON (closed) position.

2.Install 15 Amp fuse in control panel.

3.Set generator’s system switch to AUTO.

4.Push MANUAL OVER-RIDEbutton on control panel.

NOTE: When the home generator is started for the very first time, it will require that air in the gaseous fuel lines be purged. This may take a few minutes.

5.DO NOT crank engine for more than 10 seconds, then pause for 10 seconds to reduce heat in the starter.

6.Repeat process until engine starts.

7.Listen for unusual noises, vibration or other indications of abnormal operation. Check for oil leaks while engine runs.

8.Let engine warm up for about five minutes to allow internal temperatures to stabilize.

9.Connect an accurate AC voltmeter and a frequency meter to check generator output at load side of circuit breaker. Voltage should be 239‑262 Volts, frequency should be 62.0 - 62.5 Hz.

NOTE: If either parameter is outside these ranges, perform the Engine Adjustments described below.

10.Check generator output between one of the generator connection lugs and the neutral lug, then between the other generator connection lug and the neutral lug.

In both cases, voltage reading should be between 119‑131 Volts.

11.Push and hold MANUAL OVER-RIDEbutton on control panel again until engine stops.

IMPORTANT: DO NOT proceed until you are certain that generator AC voltage and frequency are correct and within the stated limits. To obtain the proper generator frequency, see Engine Adjustments.

Engine Adjustment

Each home generator unit leaves the factory set for either NG or LP gas operation. There are regional variances in the composition of natural gas. If the generator output voltage or frequency measured during Initial Start-Up (paragraph #9) is outside the listed ranges, the combustibility of the gas supplied at the installation site may be substantially different from the fuel used at the factory.

To adjust the engine for this difference, proceed as follows.

1.Open the oil drain and control panel access doors.

2.Remove the four screws that hold the circuit breaker cover to the air intake guard.

3.Connect an accurate frequency meter to the line side of the generator’s main circuit breaker.

4.Ensure that the 15 Amp fuse is installed.

5.Set the generator’s main circuit breaker ON.

6.Set the generator’s system switch to AUTO.

7.Push MANUAL OVER-RIDEbutton on control panel. When the engine starts, allow it to warm up for five minutes.

16

BRIGGSandSTRATTON.COM

Image 16
Contents Home Generator System Where to Find Us Date of Purchase GeneratorEngine Model Number Model Revision Serial NumberTable of Contents Safety Rules Hazard Symbols and MeaningsPage Installation Never operate generator without protective housing or coversInstaller Responsibilities Unpacking PrecautionsShipment Contents Equipment DescriptionGenerator Location Home Generator LocationGeneral Location Guidelines Fuel and Electrical Inlet Locations Lifting the GeneratorAccess Doors To Open an Access DoorTo Close an Access Door Gaseous Fuel SystemNo leakage is permitted Fuel Consumption Natural Gas LP VaporFuel Pipe Sizing LP Vapor NaturalPole Connector Plug System Connectors+12 Volt DC, .5 Amp Output Internal power supply Transfer Switch Communication Fault Detection SystemGenerator AC Connection System Grounding the GeneratorSystem Control Panel Final Installation ConsiderationsFuel Supply System Engine Adjustment Initial Start-up No LoadPage Schematic Wiring Diagram Setting Exercise Timer Installation InspectionControls OperationGenerador doméstico Dónde encontrarnos Fecha de compra GeneradorMotor Número de Modelo Revisión Número de SerieInstrucciones importantes de seguridad Instalación Mandos UtilizaciónSímbolos de Peligro y Significados BRIGGSandSTRATTON.COMTensión peligrosa Ate para arriba el pelo largo y quite la joyeríaInstala el fusible se puede producir el arranque del motor No modifique al generador en ninguna formaInstalación Ubicación del Generador Ubicación del Sistema de Generador de DomésticoPautas Generales para la Ubicación del Generador Dimensiones de la Entrada para Electricidad y Combustible Elevación del GeneradorPuertas de Acceso Sistema de combustible gaseosoPara abrir una puerta de acceso Para cerrar una puerta de accesoSe debe contar también con una abertura para manómetro Dimensiones de la Cañería de Combustible Consumo de CombustibleGas Natural Vapor de PL Vapor de GasConexiones de Sistema Cableado para toma de 10 polosSalida de +12 V CC y 0,5 a Fuente de alimentación interna Cableado para toma bipolarSistema de Conexión de c.a. del Generador Interconexiones del Circuito de ControlComunicación del conectador Conexión a Tierra del GeneradorPanel de Control del Sistema Sistema de Suministro de CombustibleAjuste del Motor Arranque inicial sin cargaInstale el fusible de 15 Amperios en el panel de control Mandos UtilizaciónSecuencia de operación automática Cargue el generador a plena cargaInspección posterior a la instalación Configuración del temporizador de prácticaTemporizador de enfriamiento del motor Manuel d’Installation et Démarrage Où nous trouver Date d’achat GénératriceMoteur Numéro de modèle Révision Numéro de sérieDirectives de sécurité importantes Installation Commandes FonctionnementSymboles de Danger et Moyens Directives de sécurité importantesSécurité Certains composants de ce produit ainsi que lesTension dangereuse Avis Responsabilités de l’Installateur Description de l’équipementResponsabilités de l’Acheteur Précautions Lors du DéballageInstallez l’unité à l’extérieur Seulement Emplacement du Génératrice d’état d’AttenteDégagement Autour de la Génératrice Soulèvement de la Génératrice Portes d’Accès Le système de combustible gazeuxRetrait des commandes La sortie pour manomètre permet l’installation temporaireAucune fuite ne peut être tolérée CapacitéDimension du Réservoir de Propane Nécessaire Consommation de CombustibleGas Naturel Vapeur PL Grosseur du Tuyau de CombustibleConnexions de système Interconnexions du Circuit de Commande Mise à la Masse de la GénératriceCommunication du commutateur de transfert Système de Détection des PannesConsidérations pour l’installation finale Tableau de Commande du SystèmeSystème d’Alimentation en Combustible Démarrage initial sans charge Réglage du MoteurRéglez l’interrupteur de système de la génératrice sur Auto Recommencez le processus jusqu’à ce que le moteur démarreFrançais Commandes Vérification installationFonctionnement Séquence de fonctionnement automatique