Installation

Figure 36. Single-circuit evaporator coil with two distributors

Single-Circuit Condensing Units: Evaporator Coil with Two Distributors (see Figure 36)

1Pitch the liquid line slightly—

1 inch/10 feet [1 cm/3 m]—so the refrigerant drains toward the evaporator.

2Provide one expansion valve per distributor.

3Slightly pitch the outlet line from the suction header toward the suction riser—that is, 1 inch/

10 feet [1 cm/3 m] in the direction of flow. Use the tube diameter that matches the suction-header connection.

36

4Arrange the suction line so the refrigerant gas leaving the coil flows downward, past the lowest suction-header outlet, before turning upward. Use a double- elbow configuration to isolate the thermal expansion valve bulb from other suction headers.

5For horizontal tubing, use the tube diameter recommended by the condensing unit manufacturer.

6For the vertical riser, use the tube diameter recommended by the condensing unit manufacturer. Assure the top of the riser is higher than the evaporator coil.

7Pitch the suction line slightly—

1 inch/10 feet [1 cm/3 m]—so the refrigerant drains toward the evaporator.

8Insulate the suction line.

9Only use a “trim” solenoid valve for constant-volume, humidity- sensitive applications. For all other applications, install a single solenoid valve (the “pumpdown” solenoid valve) between the liquid-line filter drier and the sight glass.

CAH-SVX01A-EN

Image 36
Contents Custom Climate Changer Air Handlers JulyCAH-SVX01A-EN Unit Description Protecting EnvironmentContents Wiring Sizes Connections Operating EnvironmentControls Factory-Mounted ControlsUltraviolet UV Germicidal Irradiation Lights optional Receiving Checklist Resolving Shipping DamageJob Site Storage Recommendations Use Canvas OnlyPre-Installation Requirements General Storage Preparing the Unit SiteLong-Term Storage Outdoor Storage ConsiderationsRoof Curb Installation Typical Curb Installation ChecklistLifting and Rigging General Lifting ConsiderationsUnit Assembly Assembly HardwareTCP Model Assembly Instructions Joining Sections Edge-to- EdgeTCP Base Section Assembly Typical TCP base assemblyInstallation TCP Wall Section Assembly Typical TCP Outdoor Roof Section Assembly TypicalIndoor Roof Assembly Complete Installation TCP Indoor Roof Section Assembly TypicalBase to Wall Assembly Complete TCC Model Assembly Instructions Joining sections Edge to EdgeApply butyl tape to shipping splits Add caulk along the seam Join internal shipping split frame TCC wall sections assembly typical Installation TCC indoor roof sections assembly typicalInstallation TCC outdoor roof sections assembly typical Join outdoor roof panels at the seamsTrim roof joint strip Component Installation Requirements Isolator AdjustmentDuct Connections FansTraq Dampers Control DampersMagnahelic Air Filter Gage Installation Air Filters Front Load FiltersOutdoor Unit Weather Hoods Bag or Cartridge FiltersUse a Backup Wrench Coil Piping ConnectionsGeneral Recommendations Prevent Coil DamageInstallation Drain Pan Trapping Water DamageInstallation Steam Coil Piping Coil DamageInstallation Water Coil Piping Typical piping for type 5W one-row water coilInstallation Refrigerant Coil Piping Liquid LinesValve Damage Type F refrigerant coil with packed elbowExamples of Field-Installed Evaporator Piping Single-circuit evaporator coil with one distributorSingle-circuit evaporator coil with two distributors Single-circuit evaporator coil with four distributors Dual-circuit evaporator coil with two distributors Dual-circuit evaporator coil with four distributors Dual-circuit evaporator coil with eight distributors Wiring Hazardous Voltage withUse Copper Conductors Only CapacitorsJunction box mounting and wiring details External Insulating RequirementsPre-Startup Checklist Fan-Related ChecksCoil-Related Checks Proper Water Treatment Motor-Related ChecksUnit Operation General ChecksCalculate Motor Voltage Imbalance Startup Tension the Fan Belt Tension Belts CorrectlyStartup Determine Fan Speed Sheave AlignmentMultibelt Check Routine Maintenance Air Filters Throwaway FiltersPermanent Filters Front Load FiltersInspecting and Cleaning Fans Drain PansFans Bearing Set Screw AlignmentFan Bearing Lubrication Fan Motor InspectionCoils Steam and Water CoilsType K Cooling Coils Refrigerant CoilsMoisture Purge Cycle Internal Insulation Replacement of ultraviolet bulbs Ultraviolet UV Germicidal Irradiation LightsTroubleshooting Alignment section on CAH-SVX01A-EN CAH-SVX01A-EN Trane