Trane CAH-SVX01A-EN manual Installation Air Filters, Front Load Filters

Page 26

Installation

Air Filters

Front Load Filters

Most filters in custom units are installed in unitary sheet metal frames. Filters are secured with a metal clip. There are several different styles.

To install filters:

1Disconnect power to the unit.

2Open or remove the filter clip.

3Remove the filter from the rack.

4Install new filters with the directional arrows pointing in the direction of airflow.

5Secure the filter using the appropriate clip for each filter.

Review Figure 21 through Figure 24 for an explanation of the methods for securing the different types of filters.

The filters are often installed in a pre/post filter configuration. Be sure to note the order of installation.

Note: Filters must have an airtight seal to prevent air bypass.

￿WARNING Hazardous Voltage with Capacitors!

Disconnect all electric power, including remote disconnects and discharge all motor start/run capacitors before servicing. Follow proper lockout/tagout procedures to ensure the power cannot be inadvertently energized. For variable frequency drives or other energy storing components provided by Trane or others, refer to the appropriate manufacturer’s literature for allowable waiting periods for discharge of capacitors. Verify with an appropriate voltmeter that all capacitors have discharged. Failure to disconnect power and discharge capacitors before servicing could result in death or serious injury.

Figure 21. C-70 fastener holds 2-inch filter

Figure 22. C-86 fastener (shown) or C- 77 fastener holds 4-inch pleated filters

Figure 23. Bag filter show with C-70 fastener

Figure 24. C-80 spring fastener secures cartridge

Side Load Filters

Most filters in custom units are installed in unitary sheet metal frames. If unit is provided with side access rack, do the following for installation:

2-inch or 4-inch flat filters.

1Disconnect the power to the unit.

2Open the filter section access door and remove the filters and block-offs from their installed position.

3Slide the filter into the rack.

4Some side load racks will be provided with block-off plates. Install them into the rack last before closing the door.

5Close and secure the door, making certain the door closes snug against the block-off (see Figure 25).

26

CAH-SVX01A-EN

Image 26
Contents Custom Climate Changer Air Handlers JulyCAH-SVX01A-EN Unit Description Protecting EnvironmentContents Controls Wiring Sizes ConnectionsOperating Environment Factory-Mounted ControlsUltraviolet UV Germicidal Irradiation Lights optional Job Site Storage Recommendations Receiving ChecklistResolving Shipping Damage Use Canvas OnlyLong-Term Storage Pre-Installation Requirements General StoragePreparing the Unit Site Outdoor Storage ConsiderationsRoof Curb Installation Typical Curb Installation ChecklistLifting and Rigging General Lifting ConsiderationsUnit Assembly Assembly HardwareTCP Model Assembly Instructions Joining Sections Edge-to- EdgeTCP Base Section Assembly Typical TCP base assemblyInstallation TCP Wall Section Assembly Typical TCP Outdoor Roof Section Assembly TypicalIndoor Roof Assembly Complete Installation TCP Indoor Roof Section Assembly TypicalBase to Wall Assembly Complete TCC Model Assembly Instructions Joining sections Edge to EdgeApply butyl tape to shipping splits Add caulk along the seam Join internal shipping split frame TCC wall sections assembly typical Installation TCC indoor roof sections assembly typicalInstallation TCC outdoor roof sections assembly typical Join outdoor roof panels at the seamsTrim roof joint strip Duct Connections Component Installation RequirementsIsolator Adjustment FansMagnahelic Air Filter Gage Traq DampersControl Dampers Installation Air Filters Front Load FiltersOutdoor Unit Weather Hoods Bag or Cartridge FiltersGeneral Recommendations Use a Backup WrenchCoil Piping Connections Prevent Coil DamageInstallation Drain Pan Trapping Water DamageInstallation Steam Coil Piping Coil DamageInstallation Water Coil Piping Typical piping for type 5W one-row water coilInstallation Refrigerant Coil Piping Liquid LinesValve Damage Type F refrigerant coil with packed elbowExamples of Field-Installed Evaporator Piping Single-circuit evaporator coil with one distributorSingle-circuit evaporator coil with two distributors Single-circuit evaporator coil with four distributors Dual-circuit evaporator coil with two distributors Dual-circuit evaporator coil with four distributors Dual-circuit evaporator coil with eight distributors Use Copper Conductors Only WiringHazardous Voltage with CapacitorsJunction box mounting and wiring details External Insulating RequirementsCoil-Related Checks Proper Water Treatment Pre-Startup ChecklistFan-Related Checks Motor-Related ChecksCalculate Motor Voltage Imbalance Unit OperationGeneral Checks Startup Tension the Fan Belt Tension Belts CorrectlyStartup Multibelt Check Determine Fan SpeedSheave Alignment Routine Maintenance Permanent Filters Air FiltersThrowaway Filters Front Load FiltersFans Inspecting and Cleaning FansDrain Pans Bearing Set Screw AlignmentFan Bearing Lubrication Fan Motor InspectionType K Cooling Coils CoilsSteam and Water Coils Refrigerant CoilsMoisture Purge Cycle Internal Insulation Replacement of ultraviolet bulbs Ultraviolet UV Germicidal Irradiation LightsTroubleshooting Alignment section on CAH-SVX01A-EN CAH-SVX01A-EN Trane