TCC wall sections assembly (typical)

Verify external unit squareness.

Apply the 1.25-inch x 0.33-inch ribbed butyl tape to the exterior of the walls covering the seam of the two adjoining sections (see method sheet).

Install seam cap over the butyl, uniformly straddling the splits. Secure with the provided number 10 sheet metal screws (see Figure 16).

Installation

TCC indoor roof sections assembly (typical)

Verify external unit squareness.

Apply the 1.25-inch x 0.33-inch ribbed butyl tape to the exterior of the roofs covering the seam of the two adjoining sections (see method sheet).

Install seam cap over the butyl, uniformly straddling the splits. Secure with the provided number 10 sheet metal screws.

Figure 16. Install seam cap over the butyl tape

CAH-SVX01A-EN

21

Image 21
Contents July Custom Climate Changer Air HandlersCAH-SVX01A-EN Protecting Environment Unit DescriptionContents Operating Environment Wiring Sizes ConnectionsControls Factory-Mounted ControlsUltraviolet UV Germicidal Irradiation Lights optional Resolving Shipping Damage Receiving ChecklistJob Site Storage Recommendations Use Canvas OnlyPreparing the Unit Site Pre-Installation Requirements General StorageLong-Term Storage Outdoor Storage ConsiderationsTypical Curb Installation Checklist Roof Curb InstallationGeneral Lifting Considerations Lifting and RiggingAssembly Hardware Unit AssemblyJoining Sections Edge-to- Edge TCP Model Assembly InstructionsTCP base assembly TCP Base Section Assembly TypicalTCP Outdoor Roof Section Assembly Typical Installation TCP Wall Section Assembly TypicalInstallation TCP Indoor Roof Section Assembly Typical Indoor Roof Assembly CompleteBase to Wall Assembly Complete Joining sections Edge to Edge TCC Model Assembly InstructionsApply butyl tape to shipping splits Add caulk along the seam Join internal shipping split frame Installation TCC indoor roof sections assembly typical TCC wall sections assembly typicalJoin outdoor roof panels at the seams Installation TCC outdoor roof sections assembly typicalTrim roof joint strip Isolator Adjustment Component Installation RequirementsDuct Connections FansTraq Dampers Control DampersMagnahelic Air Filter Gage Front Load Filters Installation Air FiltersBag or Cartridge Filters Outdoor Unit Weather HoodsCoil Piping Connections Use a Backup WrenchGeneral Recommendations Prevent Coil DamageWater Damage Installation Drain Pan TrappingCoil Damage Installation Steam Coil PipingInstallation Typical piping for type 5W one-row water coil Water Coil PipingLiquid Lines Installation Refrigerant Coil PipingType F refrigerant coil with packed elbow Valve DamageSingle-circuit evaporator coil with one distributor Examples of Field-Installed Evaporator PipingSingle-circuit evaporator coil with two distributors Single-circuit evaporator coil with four distributors Dual-circuit evaporator coil with two distributors Dual-circuit evaporator coil with four distributors Dual-circuit evaporator coil with eight distributors Hazardous Voltage with WiringUse Copper Conductors Only CapacitorsExternal Insulating Requirements Junction box mounting and wiring detailsFan-Related Checks Pre-Startup ChecklistCoil-Related Checks Proper Water Treatment Motor-Related ChecksUnit Operation General ChecksCalculate Motor Voltage Imbalance Tension Belts Correctly Startup Tension the Fan BeltStartup Determine Fan Speed Sheave AlignmentMultibelt Check Routine Maintenance Throwaway Filters Air FiltersPermanent Filters Front Load FiltersDrain Pans Inspecting and Cleaning FansFans Bearing Set Screw AlignmentFan Motor Inspection Fan Bearing LubricationSteam and Water Coils CoilsType K Cooling Coils Refrigerant CoilsMoisture Purge Cycle Internal Insulation Ultraviolet UV Germicidal Irradiation Lights Replacement of ultraviolet bulbsTroubleshooting Alignment section on CAH-SVX01A-EN CAH-SVX01A-EN Trane