General
Information
Figure 8. CDHE/F/G sequence of operation: auto to running
This diagram shows the sequence of | Figure 9. CDHE, CDHF, and CDHG sequence of operation: running |
| |
operations for a start of the first |
|
compressor on a duplex chiller. The |
|
‘First’ compressor will be determined |
|
by the type of duplex start selected. |
|
Staging Second Compressor On: |
|
This diagram shows the sequence of |
|
operations where the ‘First’ |
|
compressor is all ready running, and |
|
the ‘second’ compressor is staged |
|
on. The ‘First’ and ‘Second’ |
|
compressor will be determined by |
|
the type of duplex start selected |
|
15 |