Unit Shutdown

Unit Shutdown Procedures

Daily Unit Shutdown

Note: Refer to Start-Run Shutdown sequence in General Information Overview Sequence of Operation.

1.Press STOP.

2.After compressor and water pumps shutdown turn Pump Contactors to OFF or open pump disconnects.

Seasonal Unit Shutdown

CAUTION

Oil Pump Heater

Operation!

CONTROL POWER DISCONNECT SWITCH MUST REMAIN CLOSED TO ALLOW OIL SUMP HEATER OPERATION. Failure to do this will allow refrigerant to condense in the oil pump.

3.Open all disconnect switches except the control power disconnect switch.

4.Drain the condenser piping and cooling tower, if used. Rinse with clean water.

5.Remove the drain and vent plugs from the condenser headers to drain the condenser. Air dry bundle of residual water.

6.Once the unit is secured for winter, the maintenance procedures described under “Annual Maintenance” in the Periodic Maintenance section of this manual should be performed by qualified Trane service technicians.

Note: During extended shutdown, be sure to operate the purge unit for a 2- hour period every two weeks. This will prevent the accumulation of air and noncompensable in the machine. To start the purge, change the purge mode to ON in the DynaViewSettings Purge Menu. Remember to turn the purge mode to AUTO after the 2-hour run time.

Trouble Analysis

If the ALARM indicator on the control panel is flashing, an MMR diagnostic has occurred. Refer to Diagnostic section for trouble shooting information.

CDHF-SVU01C-EN

91

Image 91
Contents X39640670030CDHF-SVU01C-EN Read these carefully Contents Unit Nameplate General InformationLiterature change About this manualGeneral Information = 560 3 stage 935 2 stage Y = 500 3 stage 835 2 stage Control Optional Packages Commonly Used AcronymsGeneral Duplex unit components front view OverviewGeneral Duplex unit components 2 stage compressor Compressor 1 or 2 2 Stage Cooling CyclePressure enthalpy curve 3 stage compressor Pressure enthalpy curve 2 stage compressor DynaView Human Interface TechView Chiller Service ToolTimeline Text Figures Power Up DiagramSoftware Operation Overview Diagram Software States FigureStaging Second Compressor On CDHE/F/G sequence of operation auto to runningSatisfied Setpoint Staging Second Compressor OffCDHF/G sequence of operation lead 1/lag CDHE/F/G sequence of operation lead 2 lag Fixed Sequence Compressor 2 / CompressorCDHF/G sequence of operation equalize starts and hours Sequencing Balanced Starts and HoursCDHF/G sequence of operation combined start Simultaneous Compressor Start/ StopClear Restart Inhibit Restart Inhibit Start to Start Time SettingRestart Inhibit Restart Inhibit Free StartsOil and Refrigerant Pump Surface TemperaturesOil refrigerant pump circuit 1 or 20 100 percent RLA Base Loading Control AlgorithmGeneral Information Sequence of operation ice making running to ice making Ice Machine ControlHot Water control Control Panel Devices and Unit Mounted Devices Unit Control Panel UCPUnit Control Panel UCP User-defined language support Variable water flow through the evaporatorDynaView main processor Operator InterfaceOperator Interface How It Works Chiller Stop Prevention/Inhibit FeatureTop Level Mode Description System Reset Reference Main Screen Data Fields Table Chiller Operating ModeCircuit Operating Mode Main ScreenDiagnostic Screen Back button provides navigation back to the chiller screen Operator Interface Reports Report MenuReport name Circuit Condenser Report name System EvaporatorReport name Circuit Evaporator Report name System CondenserReport name System Ashrae Chiller Log Historic Diagnostics LogHeader Screen Setting Tab screens provides a userChiller Feature SettingsPurge System Mode OverridesCircuit Mode Overrides Display SettingsOperator Interface Operator Interface Operator Interface Operator Interface Operator Interface Binding Interprocessor CommunicationInter Processor Communications IPC3 IPC3 Definitions Bus ManagementControl panel components layout Control System ComponentsControl System Components Control Panel Devices Compressor Running Relay Machine Shutdown Manual Reset MMRHead Relief Request Output Maximum Capacity RelayExop Refrigerant Monitor Input 1A17Cdrp Condenser Refrigerant Pressure Output Trmm TRM4 Tracer Comm 4 interfaceEpro Enhanced Protection Pressure based Temperature basedCdrp Refrigerant Pressure Output Option 1A15 Condenser Pressure OutputRefrigerant Differential Pressure Indication Output Percent RLA Output Gbas Generic Building Automation SystemWpsr WFC Water Pressure Sensing Option Module CharacteristicsExternal Chilled Water Setpoint Ecws External Current Limit Setpoint1A13, 1A18, 1A19, 1A20 Dual Binary input module 1A8, 1A9, 1A11, 1A12 Quad Relay Output Status1A14 Communication interface Module 1A15, 1A16, 1A17, 1A21 Dual Analog Input/output Module Recommended Length to Run external Output signalsAnalog Input Unit mounted devices Control System Components Control System Components Electrical Sequence Control Sequence of OperationUCP and Wye-Delta Starter Control Circuits Delay time 200 msec. Opens 2K1 Control Sequence of Operation Test and start timing sequence Control Sequence OperationAFD Machine Protection Adaptive Control Momentary Power Loss MPL ProtectionOverload trip time versus percent RLA Current Overload ProtectionCurrent Limit Protection Phase Loss ProtectionReverse Rotation Protection SoftLoading Differential to Start or StopMinimum and Maximum Capacity Limit Evaporator Limit Leaving Water Temperature CutoutHead Relief Relay Low Refrigerant Temperature CutoutCutout strategy Condenser Limit Restart Inhibit High Vacuum Lockout Oil Temperature Control Return Water Controls Chilled Water Reset CWROutdoor Air Temperature Maximum ResetEquation Values for start reset typesDegrees of Reset Constant ReturnOutdoor air temperature versus degrees of reset Reset RatioReset function for return CWR Reset Ratio = 50% Return CWR Unit Startup Unit Start-Up ProceduresDaily Unit Start-Up Mode Live Electrical ComponentsToxic Hazards Seasonal Unit Start-UpSeasonal Unit Shutdown Unit Shutdown ProceduresUnit Shutdown Oil Pump Heater OperationRecord Keeping Forms Periodic MaintenanceDaily Maintenance and Checks Moisture ContaminationEvery 3 Months Weekly MaintenanceNormal Chiller Operating Characteristics Hazardous Voltage w/CapacitorsAnnual Maintenance Off-Season MaintenanceCompressor Oil Change Oil MaintenanceOil Change Procedure Heater DamageReplacing Oil Filter Oil Filter ReplacementHazardous Voltage w/ Capacitors MaintenanceOil Supply System Problems Other Maintenance RequirementsFront View with Refrigerant Pump Rotary valve in drain positionRefrigerant Charge Contains RefrigerantProper Water Treatment Recovery and Recycle ConnectionsLeak Testing Cleaning the CondenserControl Settings Adjustments Cleaning the EvaporatorUnit Corrosion Damage Unit Preparation Purge System103 104 105 106 107 108 109 110 111 112 113 114 115 Trane