Pre-Operation Checks

Pre-Operation Checks

Check of Electrical Items

After completing all the installation steps and before applying line power to the system, carefully check the following items:

1.Verify AC line voltage at source matches control rating.

2.Inspect all power terminations for workmanship and tightness.

3.Verify control and motor are grounded to each other and the control is connected to earth ground.

4.Check incoming signal wiring for accuracy.

Be certain all brake coils, contactors, and relay coils have noise suppression. This should be an R-C filter for AC coils and reverse polarity diodes for DC coils. MOV type transient suppression is not adequate.

Check of Electrical Items WARNING: MAKE SURE THAT UNEXPECTED OPERATION OF THE MOTOR SHAFT DURING START-UP WILL NOT CAUSE INJURY TO PERSONNEL OR DAMAGE TO EQUIPMENT.

Check of Motors/Couplings

Verify freedom of motion for all motor shafts and that all motor couplings are tight without backlash.

Verify the holding brakes, if any, are properly adjusted to fully release and set to the desired torque value.