14. IQ Network
Point to point configuration
A
B
Image14-4
Incase of a temporaryconfig uration (demo purposes) one can use the point to point configuration, the con-
nection being done via RJ45 connections using a crossed UTP cable.
14.4.2 Installing the software
AnAdministrato r password has been installed for security reasons (worm and virus protection):
Password : Barco (case sensitive !)
Necessary parts
installation CD (delivered)
•PC
How to install the client software ?
1. Install the client software from the CD ( Setup file )
How to install the server software ?
1. The server software is by default installed on the projector.
if necessary,reinstall it from the C D.
TheCD co ntaining the server software and the client tools are delivered with the projector. They can always
bedownloade dfrom thesecured PartnerZone Web site : https://secure.barco.com/presentation/
14.4.3 Start up of the iQ Pro Server
Starting up
There are 2 methods to start up the iQ Pro Server
Manual start up (viathe General me nu)
Automaticstartup at projector startup: this is done by defining the state ofthe iQ Pro Server during a “Projector ON state” and
a“Projector standby state” .
Manual start up: How to start up/shut down/reset the iQ Pro Server ?
1. Press MENU to activate the Toolbar
2. Press to select General
3. Press to Pull down the General menu
4. Use or to select iQ Pro Server
5. Press to open the menu
6. Use or to select ON/OFF/Reset (image 14-5)
7. Press ENTER
R5976491 IQ PRO G500 01/02/2007 127