2-5

Installation Procedure

There are two installation procedures presented in the following paragraphs. Each procedure is a summary of the steps you will follow to install your Compaq ProLiant 3000 server. The procedure you will use depends on whether you are installing a rack-mount model or a tower model server. Detailed instructions for each of the numbered steps are included in later chapters of this guide.

Installing a Rack Mount Model

1.Select an appropriate site for your rack. See the Rack Planning and Installation Guide for site selection criteria.

2.Make sure that that stabilizer feet are installed on the rack.

3.Unpack the server.

4.Unpack the rack mounting hardware.

5.Install any hardware options in the server. See Chapter 4 and the options kits for detailed instructions.

6.To make the server lighter and more manageable, do not install SCSI drives in the server until after you load the server into the rack. You may also lighten the server by removing the power supplies and reinstalling them after you have mounted the server in the rack.

7.Set switches: processor board switches, system board switches, and SCSI ID settings.

8.Attach rack mounting hardware to the rack and to the server. See Chapter 3 for detailed instructions.

9.Slide the server into the rack. See Chapter 3.

10.Attach the cable management arm to the cable management arm bracket. See Chapter 3.

11.Attach the optional cable support to the back of the rack. The cable support is needed only if you are routing cables from one side of the rack to the other. See Chapter 3.

ProLiant 3000 Setup and Installation Guide

Page 32
Image 32
Compaq 3000 manual Installation Procedure, Installing a Rack Mount Model