Site Requirements

The PowerConnect 28xx can be mounted in a standard equipment rack, placed on a tabletop, or mounted on the wall.

Before installing the device, verify that the site selected for the device meets the following site requirements:

Power — The device is installed within 1.5 m (5 feet) of a grounded, easily accessible outlet 220/110 VAC, 50/60 Hz. If the device has two power supplies, the site should have two power outlets with different power feeders.

General — Ensure that the power supply is correctly installed.

Clearance — There is adequate frontal clearance for operator access. Allow clearance for cabling, power connections, and ventilation.

Cabling — Cabling is routed to avoid sources of electrical noise such as radio transmitters, broadcast amplifiers, power lines, and fluorescent lighting fixtures.

Ambient Requirements — The ambient device operating temperature range is 0 to 45 °C (32 to

113 °F) at a relative humidity of up to 95%, non-condensing. Verify that water or moisture cannot enter the device case.

Unpacking

Package Contents

While unpacking the device, ensure that the following items are included:

The device

AC power cable

Self-adhesive rubber pads (for on-shelf installation)

Rack-mount kit for installation

Documentation CD

Product Information Guide

Unpacking the Device

To unpack the PowerConnect device:

NOTE: Before unpacking the device, inspect the packaging and report any evidence of damage.

1Place the box on a clean flat surface.

2Open the box or remove the box top.

3Carefully remove the device from the package and place it on a secure, stable and clean surface.

4Remove all packing material.

28