CHAPTER 9: PROGRAMMING GROUP 0 - GLOBAL METER SETUP

GROUP 0, FUNCTION 3 — SYSTEM CONFIGURATION

9.3.2Switching Communication Protocols, EI-BUS, MODBUS RTU/ASCII, DNP 3.0

For EI-BUS protocol: PACK 2, Switch C is DOWN, Switch D is DOWN.

For MODBUS protocol, ASCII framing: PACK 2, Switch C is UP, Switch D is UP.

For MODBUS protocol, RTU framing: PACK 2, Switch C is DOWN Switch D is UP.

For DNP 3.0 protocol: PACK 2, Switch C is UP, Switch D is DOWN.

When programming for MODBUS protocol configuration of LIPA (Long Island

Power Authority) mapping options may be performed through communication.