Setup

System Assembly

When the system is shipped from the factory some items may be shipped loose. Perform the following instructions to properly install each of the component items.

1.For cart and boom systems only, install legs:

a.With the system still on the pallet, use the sup- plied hardware to install the legs onto the base as shown below. The two longer legs should be installed on the air control panel side of the machine. The two non-locking casters should be installed on the two longer legs.

2. Connect heater (if ordered):

Improperly installed or connected equipment may create a hazardous condition that can cause fire, explosion, or electric shock.

Refer to heater manual listed on page 3 for detailed instructions and warnings.

You must have a qualified electrician connect heater wiring. Ensure wiring and installation com- ply with local electrical codes for hazardous areas.

Wiring, wiring connections, switches, and electrical distribution panel must all meet flame-proof (explo- sion-proof) requirements.

a.Use supplied hardware to install heater onto pole as shown below. Position the heater to ease hose routing between pump and heater. See Heater Kits manual for bolt hole patterns.

ti18523c

b.Use a forklift to raise the system off of the pallet, remove the pallet, then place item directly on the floor.

Viscon Heater Shown

ti18529b

b. Connect heater electrical connections. See heater manual listed on page 3 for detailed instructions.