Setup
18 3A2012J
System Assembly
When the system is shipped from the factory some
items may be shipped loose. Perform the following
instructions to properly install each of the component
items.
1. For cart and boom systems only, install legs:
a. With the system still on the pallet, use the sup-
plied hardware to install the legs onto the base
as shown below. The two longer legs should be
installed on the air control panel side of the
machine. The two non-locking casters should
be installed on the two longer legs.
b. Use a forklift to raise the system off of the pallet,
remove the pallet, then place item directly on
the floor.
2. Connect heater (if ordered):
a. Use supplied hardware to install heater onto
pole as shown below. Position the heater to
ease hose routing between pump and heater.
See Heater Kits manual for bolt hole patterns.
b. Connect heater electrical connections. See
heater manual listed on page 3 for detailed
instructions.
ti18523c
Improperly installed or connected equipment may
create a hazardous condition that can cause fire,
explosion, or electric shock.
Refer to heater manual listed on page 3 for
detailed instructions and warnings.
You must have a qualified electrician connect
heater wiring. Ensure wiring and installation com-
ply with local electrical codes for hazardous areas.
Wiring, wiring connections, switches, and electrical
distribution panel must all meet flame-proof (explo-
sion-proof) requirements.
Viscon Heater Shown
ti18529b