UPS Only Installation
W A R N I N G
Only qualified service personnel (such as a licensed electrician) should perform the UPS installation and initial startup. Risk of electrical shock.
Use the following procedure to hardwire the UPS:1.Verify that the electrical connections to the installation site have been properly installed.
2.A
Compare the circuit breaker ratings and wire sizes to the ones in the following wiring table:
Table 1. Circuit Breaker RatingsUPS Capacity | Input Circuit Breaker Rating | Minimum Wire Size* |
|
8 kVA | 60A | 4 AWG (21.2 mm2) | |
10 kVA | 80A | 3 AWG (26.7 mm2) | |
12 kVA | 100A | 2 AWG (33.6 mm2) | |
15 kVA | 100A | 2 AWG (33.6 mm2) |
*Use only
NOTE To accommodate the feature of easy system expandability, it is recommended that initial installation of the Powerware 9155 UPS contain wiring to support the maximum capacity of the UPS cabinet.
3.Switch off utility power to the distribution point where the UPS will be connected. Be absolutely sure there is no power.
4.Determine your equipment’s grounding requirements according to your local electrical code.
5.Verify that the UPS battery circuit breaker is in the OFF position (see Figure 5).
16 | Powerware® 9155 UPS |