Section 2 | Installation |
Introduction
There are nine basic steps required to install the Switch.
1.Unpack
2.Place or Mount the Equipment
3.Apply the IEC Laser Safety Label (If the installation contains fiber optic GBICs and is in Europe)
4.Install the GBICs
5.Connect the Switch to AC power
6.Check the
7.Cable Fibre Channel Devices to the Switch
8.Configure the chassis
9.Configure the ports
Unpack
1.Unpack the Switch from the carton. There are no packing materials or shipping fixtures located inside the chassis.
2.Ensure that the power cable has a plug that is suitable for your location.
QLogic supplies the Switch with a standard
3.GBICs (if you have ordered them from QLogic) are packaged separately.
QLogic supplies one Loopback Plug for each type of GBIC you ordered. A Loopback plug is a plug that, when fully inserted into a GBIC port, intercon- nects transmit and receive for that port. In case of a suspected GBIC failure, you may use these Loopback Plugs, in conjunction with a test, to verify the operation of a GBIC. Refer to “Fibre Channel Port
| Installation | |