Fig. 42a

A

7. CHECK THERMOSTAT CIRCUIT(S)

1.Disconnect the two external wires connected to the boiler thermostat terminals (low voltage terminal strip M4a).

2.Connect a voltmeter across these two incoming wires. Close each thermostat, zone valve and relay in the external circuit one at a time and check the voltmeter reading across the incoming wires.

3.There should NEVER be a voltage reading.

4.If a voltage does occur under any condition, check and correct the external wiring.

5.Once the external thermostat circuit wiring is checked and corrected if necessary, reconnect the external thermostat circuit wires to boiler low voltage terminal strip. Allow the boiler to cycle.

8.TESTING FOR GAS LEAKS

Prior to start-up of the boiler you must check the external tightness of the gas supply valve and confirm this in the start-up report. Inspect the entire installation including the gas meter.

WARNING: Before starting the XPak, and during initial operation, smell near the floor and around the heater for gas odorant or any unusual odor. Remove heater front door and smell interior of heater enclosure. Do not proceed with startup if there is any indication of a gas leak. Repair any leak at once.

WARNING: LPG boiler only — Your propane supplier mixes an odorant with the LPG to make its presence detectable. In some instances, the odorant can fade, and the gas may no longer have an odor. Before startup (and periodically thereafter), have the LPG supplier verify the correct odorant level in the gas.

WARNING:

-Cover endangered positions before leak testing.

-Do not spray the leak testing agent onto cables, plugs or electrical connection lines.

-Do not allow it to drip onto them either.

DANGER: Leaks may be caused to pipes and screw connections during commissioning and maintenance activities.

-Carry out a proper leak test.

-Only use approved leak detection agents for leak detection.

-Disconnect the heating system from the power supply.

-Check the exterior tightness of new pipe sections up to and including the direct sealing point on the gas burner fitting.

9.INITIAL FLUSHING OF THE SYSTEM

The whole of the heating system must be flushed both cold and hot as detailed in Fig. 42a. Open all radiator or heating valves and the boiler flow & return service valve. Drain the boiler and system from the lowest points. Open the drain valve full bore to remove any installation debris from the boiler prior to lighting. Refill the boiler and heating system.

10. PRE-OPERATION CHECKS

Before attempting the initial lighting of the appliance, the following checks must be carried out:

-Ensure all gas service valves from the meter to the appliance are open and the supply pipe has been properly purged;

-Ensure the proper electrical checks have been carried out, particularly continuity, polarity, and resistance to ground;

-Ensure the 4 AMP fuses are installed;

-Ensure the system has been filled, vented, and the pressure set to 15 p.s.i. (1 bar);

-Ensure the flue system has been installed properly and in accordance with the instructions;

-Ensure all appliance service valves are open.

11.INITIAL LIGHTING AND IGNITION SAFETY SHUTOFF DEVICE TEST

Ensure the electrical supply to the appliance is switched on. Ensure any external controls are switched to an ‘ON’ position and are

calling for heat.

Move the selector switch to the ON position ( - - F ), the appliance will now operate.

NOTICE:

After installation, the boiler must be turned ON and the thermostat set for CFH and operated with the manual gas shut-off valve below the unit closed. Allow the boiler to go through its 5 ignition tries and then lock out.The display should indicates the alarm code 10. After the test, reset the control, open the gas valve, set the thermostat to the proper setting and ensure that the boiler operates properly.

12. CHECKING GAS PRESSURE AND COMBUSTION ANALYSIS

The boiler is factory set and requires no additional adjustment once installed.

If the installation does not include a gas meter (for example LPG) and there are no means by which to calculate the gas rate, then a combustion analysis test must be carried out in accordance with local regulations to ensure the appliance is left working safely and correctly.

Additionally, if the gas valve has been adjusted, replaced, or the appliance has been converted for use with another gas type, then it becomes necessary to carry out a combustion analysis/ check to ensure that correct combustion is occurring.

If there are no means to gas rate the appliance and/or carry out a combustion analysis check, then it will not be possible to comple- te the commissioning procedure.

Details on how to carry out the combustion analysis can be found in Section 11.

NOTICE: It’s imperative that a sufficient dynamic – gas – pressure is maintained at all times. Should the dynamic gas pressure fall below an acceptable level, the appliance may malfunction or sustain damage.

13. FINAL FLUSHING OF THE HEATING SYSTEM

The system shall be flushed. Cleaners or chemicals used, must be suitable for Aluminum heat exchangers and shall be from a reputable manufacturer and shall be administered in strict accordance with the manufacturers’ instructions.

NOTICE: Chemicals used to clean the system and/or inhibit corrosion must be pH neutral, i.e. they should ensure that the level of the pH in the system water remains neutral.

Premature failure of certain components can occur if the level of pH in the system water is out of normal levels.

14.SETTING THE BOILER OPERATING TEMPERATURE The flow outlet temperature can be adjusted between 104-176°F(40-80°C) depending on the boiler configuration via the Heating thermostat knob (Fig. 1A).

If the 3-way valve is connected, the flow outlet temperature to the tank can be adjusted between 95-140°F (35-60°C) via the DHW temperature selector (Fig. 1A).

15.REGULATING THE CENTRAL HEATING SYSTEM

Fully open all radiator and circuit valves and run the appliance for both heating and hot water until heated water is circulating. If conditions are warm remove any thermostatic heads. Adjust radiator return valves and any branch circuit return valves until the individual return temperatures are correct and are approximately equal.

41

Page 41
Image 41
Raypak 120, 85 manual Check Thermostat Circuits, Testing for GAS Leaks, Initial Flushing of the System, PRE-OPERATION Checks

120, 85 specifications

The Raypak 120,85 is a prominent model in the realm of pool and spa heating solutions, designed to deliver unmatched efficiency and performance. Renowned for its robust features and innovative technologies, the Raypak 120,85 stands out as a reliable choice for homeowners seeking to maintain the perfect water temperature in their pools and spas.

One of the primary characteristics of the Raypak 120,85 is its impressive heating capacity. With a total output of 120,000 BTUs, this heater quickly and efficiently warms up water, ensuring that users can enjoy comfortable swimming conditions regardless of the outdoor temperature. The 85 indicates its ability to deliver consistent performance even in cooler climates, making it an adaptable option for various geographical locations.

The Raypak 120,85 is equipped with a state-of-the-art, copper fin tube heat exchanger, which provides superior heat transfer efficiency. This technology enhances the heater's ability to warm water rapidly while maintaining energy efficiency. Additionally, the copper material is known for its durability and resistance to corrosion, ensuring a long lifespan for the heat exchanger.

Another key feature of the Raypak 120,85 is its electronic ignition system. This innovation eliminates the need for a standing pilot light, which not only saves energy but also enhances safety by reducing the risk of gas leaks associated with traditional ignition systems. The electronic ignition provides precise control, ensuring a reliable start each time.

The Raypak 120,85 also boasts a digital display control panel, allowing users to easily monitor and adjust the water temperature settings. This intuitive interface provides accurate readings and simplifies the operation, making it accessible for all users, regardless of their technical expertise.

Furthermore, this heater is designed with a compact footprint, making it suitable for a variety of installation spaces, whether it’s in a pool equipment area or near a spa. Its robust build quality and weather-resistant design ensure that it can withstand the elements, making it a durable and long-lasting investment.

In summary, the Raypak 120,85 combines advanced heating technology, robust construction, and user-friendly features. With its high BTU output, efficient heat exchanger, electronic ignition, and digital controls, it represents a top-tier option for anyone seeking reliable and effective heating solutions for pools and spas. Whether for leisure or relaxation, the Raypak 120,85 promises to deliver an optimal swimming experience, season after season.