START-UP CHECKLIST FOR FAN-ASSISTED
RAYPAK PRODUCTS
This
GASSUPPLYDATA |
|
|
Regulator Model & Size | _________ / | CFH |
Gas Line Size (in room) | ____________ | In. NPT |
Length of Gas Line | ____________ | Eq Ft |
Gas | ____________ |
|
( Ball, Lube cock) |
|
|
Sediment Trap | ____________ | Y/N |
Port | _______Std__ | Full |
VISUAL INSPECTION OF COMPONENTS
Verify inspection was done and condition of components are in good working order with a “yes”
Wiring Harness | _____________ Y/N |
Burner/s (flame) | _____________ Y/N |
Remote flame sense | _____________ Y/N |
VENTING |
|
Vent Size:___________ | Stack Height:_____ |
Category: _________ | sketch vent on reverse side *** |
Vent Material: | __________________ |
Vent Termination Type: | __________________ |
Combustion Air Openings: | Low __________in2 |
Ventilation air | High _________ in2 |
EMISSIONSSETTINGSANDTESTINFORMATION(ATFULLFIRE) | |
Blower Pressure Setting | ______________ In. WC |
Supply Gas Pressure | ______________ In. WC |
Verify stable pressure static & | dynamic condition |
Manifold Gas Pressure | _____________ In. WC |
Tracking Pressure (clean filter) ______________In. WC
CLEARANCES |
|
Front Clearance | _______________In. |
Right Side Clearance | _______________In. |
Left Side Clearance | _______________In. |
Rear Clearance | _______________In. |
Overhead Clearance | _______________In. |
ELECTRICAL |
|
Voltage Supply (VAC) | No Load______ Load_____ |
Voltage | _____________ VAC |
Voltage Com to Ground | _____________ VAC |
Operating Control Setting _____________deg F
Sketch plumbing on reverse side
WATER SUPPLY
Flow Rate in GPM or Delta T __________ If Avail
Measure flow rate at full fire
Number of Tanks and Size Qty____ ____ Gallons
Plumbing Size | _______________ | |
Pump Size: _________ (boiler) | Pump HP: ________ | |
Impeller trim____________ | Pump Model________ | |
Louvers __________________ | Screens____________ |
Nominal Factory Recommended Settings
See manual or card tag
See manual or card tag
See manual or card tag
The following measurements must be obtained with a Combustion Analyzer.
NOX | _____________ PPM | Less than 20 PPM (If required by Certifying Agency) |
Free Oxygen | _____________ % | See manual |
CO | _____________ PPM | Less than 170 PPM |
CO2 | _____________ % | See manual |
Model Number: ______________________________
***Note: draw venting with details, such as extractors, barometric dampers, blast dampers or draft inducers
Serial Number: _______________________________
Site Altitude Above Sea Level __________________Ft.
Job Name _______________________________________________________________________________________
Address _________________________________________________________________________________________
Physical Location of Boiler: Indoors______; Outdoors______; Ground Level______; Roof______; Below Grade______
Mechanical Contractor / Installer _______________________________________________________________________
Date and Time of
Information must be faxed to: (805)
67