Steps for setting up (also refer to Quick Start)
1. Receive and inspect the drive
vCheck that the part number printed on the label is the same as that on the
purchase order.
vRemove the Altivar from its packaging and check that it has not been damaged
in transit.
2. Check the line voltage
vCheck that the line voltage is compatible with the voltage
range of the drive (page 11).
3. Mount the drive
vMount the drive in accordance with the instructions
in this document (page 13).
vInstall any options required.
Steps 2 to 4 must
be performed with
the power off.
4. Wire the drive (page 20)
vConnect the motor, ensuring that its
connections correspond to the voltage.
vConnect the line supply, after making
sure that the power is off.
vConnect the control part.
5. Configure the drive (page 32)
vApply input power to the drive but
do not give a run command.
vSet the motor parameters
(in Conf mode) only if the factory
configuration of the drive is not
suitable.
vPerform auto-tuning.
6. Start