8 TEST RUN

Before test operation

WARNING

• Before turning on the power supply, carry out the following

To protect the compressor at

procedures.

startup. Ensure the power supply

1) Using 500V-megger, check there is 1Mor more between the

is left on for 12 or more hours

terminal block of the power supply and the earth.

before operation.

If 1Mor less is detected, do not run the unit.

 

2)Check that all the valves of the outdoor unit are fully opened.

Never push the electromagnetic contactor to carry out a forced test operation. (It is very dangerous because a protective device does not work.)

How to execute test operation

To carry out a fan operation in a single indoor unit, firstly turn off the power supply to the unit. Then short CN72 found on the P.C. board. Once completed turn the power to the unit back on and start the unit in FAN only mode. Upon completion of the test do not forget to remove the short circuit on CN72.

Using the remote controller, check the unit is in normal operation. For the operation procedure, refer to the supplied Owner’s Manual. A forced test operation can be executed in the following procedure under the condition of thermo.-OFF of room temperature.

In order to prevent the test operation from running continuously, the operation will cease after a period of 60 minutes. The unit will then return back to its original operation.

In case of wireless remote controller

Procedure

Description

 

 

1

Remove a small screw which fixes the nameplate of the receiver unit.

Remove the nameplate of the sensor section by inserting a minus screwdriver, etc into the notch at the bottom

 

of the plate, and set the Dip switch to [TEST RUN ON].

Execute a test operation with button on the wireless remote controller.

2

 

, , and

LED flash during test operation.

 

• Under status of [TEST RUN ON], the temperature adjustment from the wireless remote controller is invalid.

 

Do not use this method in the operation other than test operation because the equipment is damaged.

 

 

3

Use either COOL or HEAT operation mode for a test operation.

* The outdoor unit does not operate approx. 3 minutes after power-ON and operation stop.

 

 

4

After the test operation finished, stop the air conditioner from the wireless remote controller, and return Dip

switch of the receiver section as before.

(A 60-minutes timer clearing function is attached to the receiver section in order to prevent a continuous test

 

operation.)

 

30

NOTE

Do not use a forced operation in cases other than test operation because it applies an excessive load onto the air conditioner.

In case of wired remote controller

1, 5

 

TEMP.

 

ON / OFF

TIMER SET

FAN

MODE

TIME

SWING/FIX

VENT

FILTER

 

 

RESET TEST SET CL

UNIT

 

2, 4

3

Receiver unit

Spacer

M4 × 25 screw (2 pieces)

Procedure

 

 

Description

 

 

 

 

 

 

 

 

 

 

 

Keep the TEST button pushed down for 4 seconds or more.

 

 

 

 

 

 

 

 

 

1

 

TEST

 

 

[TEST] is displayed on the display part and the selection of the test mode is

 

 

 

 

 

permitted.

 

 

 

 

 

 

 

 

 

 

 

 

 

2

Push

ON / OFF button.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Using

MODE button, select the operation mode, [COOL] or [HEAT].

 

 

 

 

3

• Do not run the air conditioner in a mode other than [COOL] or [HEAT].

 

 

 

 

• The temperature controlling function will not work during the test operation.

 

 

 

 

 

• Fault detection will perform as usual.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

After the test operation, push the

ON / OFF button to stop the operation.

 

 

 

 

(Display part is the same as procedure 1 )

 

 

 

 

 

 

 

 

 

 

5

Push the TEST button to cancel (release from) the test operation mode.

 

 

 

 

 

 

 

 

 

 

 

 

([TEST] disappears on the display part and the status returns to normal.)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 