Automatic Operation Sequence

The generator’s control panel houses a logic control circuit board. This control board constantly monitors utility power source voltage. Should that voltage drop below a preset level, control board action will signal the engine to crank and start.

When utility source voltage is restored above a preset voltage level, the engine is signaled to shut down.

The actual system operation is not adjustable and is sequenced by sensors and timers on the control board, as follows:

Utility Voltage Dropout Sensor

This sensor monitors utility source voltage.

If utility source voltage drops below about 70 percent of the nominal supply voltage, the sensor energizes a

10 second timer. The timer is used to ‘sense’ brown-outs.

Once the timer has expired, the engine will crank and start.

Utility Voltage Pickup Sensor

This sensor monitors utility power supply voltage. When that voltage is restored above 80 percent of the nominal source voltage, a time delay starts timing and the engine will go to engine cool-down.

Engine Cool-down Timer

When the load is transferred back to the utility power source, the engine cool-down timer starts timing.

The timer will run for about one minute, then the generator will stop.

Minimum engine run time is 5 minutes.

Automatic Operation

To select automatic operation, do the following:

1.Set the main distribution panel circuit breaker that sends utility voltage to the transfer switch to ON.

2.Set the generator’s main circuit breaker to its ON position.

3.Set the system switch to AUTO.

caution

With the system switch set to AUTO, the engine may crank and start at any time without warning. Such automatic starting normally occurs when utility source voltage drops below a preset level or during the normal exercise cycle.

To prevent possible injury that may be caused by such sudden starts, always set the system switch to OFF.

Remove the 15 Amp fuse before working on or around the generator or transfer switch.

Checking Automatic Operation

To check the system for proper automatic operation, proceed as follows:

1.Turn OFF the main distribution panel circuit breaker sending power to the automatic transfer switch.

The engine will crank and start when the utility voltage drops out and the sensor has timed out. Let the system go through its entire automatic operation sequence.

2.With the generator output supplying its loads, turn ON the main distribution panel circuit breaker that supplies utility power to the automatic transfer switch.

3.The automatic transfer switch will transfer loads back to the utility power after 5 minute minimum run time and utility is restored.

4.The generator will run for an additional one minute for engine cool down, then shut down.

NOTE: If utility is restored and generator does not shut down after 10 minutes, set system switch to OFF and contact your installer or local service center.

This completes the test procedures for automatic operation. The home generator will now start automatically when utility power is lost and will supply power to the transfer switch.

20

BRIGGSandSTRATTON.COM

Image 20
Contents Watt Home Generator System Where to Find Us Date of Purchase GeneratorEngine Model Number Model Revision Serial NumberTable of Contents BRIGGSandSTRATTON.COM Safety RulesHazard Symbols and Meanings Page See Essential Circuits Installation Owner OrientationFuel Factors Lifting the GeneratorGeneral Location Guidelines Home Generator LocationGenerator Location Essential Circuits Access Covers To Remove Access CoverTo Install Access Cover and Roof Fuel and Electrical Inlet LocationsGaseous Fuel System Manometer port should be provided BRIGGSandSTRATTON.COMNatural Gas LP Vapor Fuel ConsumptionFuel Pipe Sizing 10ft 15ft 20ft 30ft 40ft 50ft 60ft 70ft 80ft 90ft 100ftFuel Comparison Chart LP Vapor NaturalGas Required Propane Tank Size+12 Volt DC, .5 Amp Output Internal auxiliary power supply System ConnectorsPole Connector Plug Transfer Switch Communication Fault Detection SystemTo install the remote LED indicator Generator AC Connection SystemFinal Installation Considerations Initial Start-up No LoadUnit Identification Label Identifies unit by serial number Features and ControlsHome Generator System Control Panel Automatic Operation OperationAutomatic Operation Sequence Setting Exercise Timer Servicing the System MaintenanceFault Detection System High Temperature Transfer Switch FaultLow Voltage Generator Engine Fail To StartGenerator Maintenance Servicing the Battery BatteryCharging the Battery Storage To Clean the GeneratorWhen Calling the Factory Troubleshooting Problem Cause CorrectionDown when loads are connected AvailableSchematic Wiring Diagram Limited Warranty Page Product Specifications Common Service PartsAt 120 Volts At 240 VoltsWatt Dónde encontrarnos Fecha de compra GeneradorMotor Número de Modelo Revisión Número de SerieProblemas Garantía Especificaciones del producto Reglas de seguridadInstalación Controles y característicasReglas de seguridad Símbolos de Peligro y SignificadosTensión peligrosa Ate para arriba el pelo largo y quite la joyeríaInstala el fusible se puede producir el arranque del motor No modifique al generador en ninguna formaInstalación Orientación para el propietarioInspección al Momento de la Entrega Factores Relacionados con el CombustiblePrecauciones al Momento del Desempaque Elevación del Generador Ubicación del Sistema de Generador de DomésticoUbicación del Generador Pautas Generales para la Ubicación del GeneradorCircuitos Fundamentales Selección de los Circuitos FundamentalesDispositivo Vatiaje de Sistema de combustible gaseoso Dimensiones de la Entrada para Electricidad y CombustiblePuertas de Acceso Se debe contar también con una abertura para manómetro Gas Natural Vapor de PL Vapor de GasCableado para toma de 10 polos Conexiones de SistemaCableado para toma bipolar Sistema de Conexión de c.a. del Generador Conexión a Tierra del GeneradorInterconexiones del Circuito de Control Comunicación del conectadorConsideraciones finales para la instalación Inspección posterior a la instalación Arranque inicial sin cargaInstale el fusible de 15 Amperios en el panel de control Controles y características Generador DomésticoAjustes. Conserve este manual para referencias futuras Calcomanía de Datos de la Unidad Identifica a laPanel de control del sistema Utilización Secuencia de operación automáticaFuncionamiento Automático Temporizador de enfriamiento del motorConfiguración del temporizador de práctica Sistema de Detección de Fallas MantenimientoParo del Sistema Baja Tensión El Motor no ArrancaBaja Frecuencia Sobrevelocidad del MotorMantenimiento del Generador Servicio la Batería BateríaCargar la Batería Si Llama a la Fábrica AlmacenamientoPara Limpiar el Generador Problemas Problemas Causa CorrecciónGarantía Limitada Especificaciones del producto Servicio común despideWatt Groupe électrogène Où nous trouver Date d’achat GénératriceMoteur Numéro de modèle Révision Numéro de sérieFonctions et commandes Règles de sécuritéFonctionnement EntreitenSymboles de Danger et Moyens Règles de sécuritéSécurité Certains composants de ce produit ainsi que lesTension dangereuse Avis Responsabilités de l’installateur Conseils au propriétaireConservez ces instructions Responsabilités de l’acheteurVérification de la livraison Facteurs relatifs au combustiblePrécautions lors du déballage Emplacement du génératrice d’état d’attente Directives générales concernant l’emplacementInstallez l’unité à l’extérieur Seulement Soulèvement de la génératriceCircuits essentiels ’illustration suivante montre les dégagements Minimum10 Sélection des circuits essentielsScie circulaire 6,5 po 16,5 cm Sécheuse électrique 750 Sécheuse gazDéshumidificateur Couverture électriquePour installer la porte d’accès et le toit Portes d’accèsLe système de combustible gazeux Pour enlever le toitAucune fuite ne peut être tolérée Il faudrait inclure une sortie pour manomètreGas Naturel Vapeur PL Propane GazConnexions de système Interconnexions du Circuit de Commande Sécurité Système de Branchement C.A. de la GénératriceNiveau de la génératrice Mise à la Masse de la GénératriceConsidérations pour l’installation finale Vérification installation Démarrage initial sans chargeEntretien Dépannage Garantie Fonctions et commandesSécurité Instalación Commandes Fonctionnement Tableau de commande de système Sécurité Instalación CommandesFonctionnement automatique FonctionnementSéquence de fonctionnement automatique Entreiten Arrêt du SystèmeSystème de Détection des Pannes Code de Nombre deAucun DEL Batterie déchargée Faible Tension de la BatterieFaible Pression d’Huile Basse TensionEntretien du Générateur Batterie Changement du filtre à huilePour mettre de l’huile dans le moteur Filtre à airRemisage Entretien de la BatteriePour Nettoyer le Générateur 26Problème Cause Solution DépannageGarantie Limitée Page Caractéristiques du produit Pièces d’entretien courant