Burnham 1100-H4 manual Install vent piping

Page 41

I. Optional Exterior Separate Horizontal Vent/Air Intake Terminal Mounting – See Figures 17, 18, 19, 20, 21 and 22.

1.Do not exceed maximum vent/air intake lengths. Refer to Table 4.

2.This installation will allow a maximum of seven (7) feet vertical exterior run of the vent/air intake piping to be installed on separate horizontal venting and indoor air horizontal venting.

NOTICE

Exterior run to be included in equivalent vent/air intake lengths.

d.At top of vent pipe length install an AL 29-4C®90° elbow so that elbow leg is opposite the building’s exterior surface.

e.If installation requires indoor air, install

AL 29-4C®45° elbow to upper AL 29-4C®90° elbow so that leg of 45° is in down direction (see Figure 21 or 22). If not using indoor air, proceed to Step f.

f.Install horizontal vent terminal (provided with boiler).

g.Brace piping if required.

3.Install vent piping.

a.Install vent piping for desired venting system.

Refer to specific section for details for vent pipe installation.

b.After penetrating wall/thimble, install an

AL 29-4C®90° elbow so that elbow leg is in the up direction.

c.Install maximum of seven (7) feet of AL 29-4C®vent pipe. Refer to Sections C through E for proper procedures for joining vent pipe and fittings.

4.Air Intake Piping (not required for indoor air).

a.Install air intake piping for desired venting system. Refer to specific section for details for air intake installation.

b.After penetrating wall, install a corrosion resistant 90o elbow so that elbow leg is in the up direction.

c.Install maximum of seven (7) feet of corrosion resistant air intake pipe.

d.At top of air intake pipe install air intake terminal (provided with boiler).

e.Brace piping if required.

Figure 17: Optional Separate Horizontal Air 3” or 4” Intake Terminal Installation

41

Image 41 Contents
8140705R9-10/08 Price $5.00 SCGImportant Information Read Carefully Page Table of Contents Dimensions Pre-Installation Do not drop boiler. Do not bump boiler jacket against floor II. Unpack BoilerRequired See Section III. Venting / Air Intake PipingVent/Air Intake Length Vent System Components Included with BoilerBurnham Vent System and Air Intake System Components General Guidelines Vent Guidelines Due to Removal of an Existing BoilerBurnham Gasketed Vent Joint Detail Install Vent Pipe, Burnham Gasketed Vent SystemVent Piping Recommended Separate Horizontal Vent/Air Intake Installation Alternate Separate Horizontal Vent/Air Intake Installation Page Page Separate Vertical Venting System See Figures 6, 7, 8A, 8B Page Vertical Vent Installation Page Page Vertical Air Intake Piping Combination Horizontal Vent System Components Install Combination Vent/Air Terminal. See FigureNon-corrosive fasteners must be used Install Air Intake Piping. See Figures 10Combination Horizontal Vent/Air Installation SCG-3 thru Page Combination Vertical Vent System Components Description Part Number SCG-3 & SCG-4Clearances to Combustibles Pre-Installation ConsiderationsGeneral Installation Requirements Page Joint Assembly Instructions Inner pipe is always cut 1 longer than the outer pipe Condensate Drains Horizontal Supports Page Tall Cone Flashing Directly On Roof or Curb Fire Stop/Wall Thimble/Support, SC FSPage Horizontal Recommended Separate Horizontal Vent Installation Alternate Separate Horizontal Vent Installation Optional Indoor Air Vent Terminal Installation Install vent piping Optional Separate Horizontal 3 Vent Terminal Installation Optional Separate Horizontal 4 Vent Terminal Installation Page Lwco Location IV. Water Piping and TrimHow to Test How to WireSupply Water Manifold Piping Page Page Gas Piping Valves Fully Open Page VI. Electrical Internal Boiler Wiring Schematic Diagram Internal Boiler Wiring Ladder Diagram System Controls and Wiring System Wiring Schematic for Single Zone Space Heating Only Page Circulator Zoned System Wiring Schematic Zone Valve Zoned System Wiring Schematic Page Modular Boiler Water Manifold Sizing VII. Modular InstallationDo not manifold vent pipes together Modular Boiler Gas Piping VIII. System Start-up Operating Instructions Yellow led flame codes Operating InstructionsIgnition Module Terminal CROSS-REFERENCE Green Led status codes Honeywell Electronic Ignition Troubleshooting Guide Sequence of Operation Gas Flow Rate in Cubic Feet Per Hour Adjust gas input rate to boilerCheck limit Low water cutoff if so equipped IX. ServicePilot Burner Location Silicone Tubing AssemblyFlue and Burner Cleanout, 1 Burner Main Burners and Firebox Procedure for Measuring Differential Pressure See FigureDifferential Pressure Switch Settings This page Left Intentionally Blank Page Page XI. Repair Parts Casting Assembly Page Base Assembly Page Base Enclosure Assembly Page FAN/CANOPY Assembly Page Burner Assemblies Page Control Panel Assembly Page Jacket Parts Miscellaneous Parts Carton Avoid Breathing Fiber Particulates and Dust Service Record Service Record Limited Warranty