Burnham 1100-H4 manual How to Wire, How to Test

Page 46

How to Wire

Ensure power is turned off to boiler.

Locate the LWCO jumper wire in the factory wiring harness. Remove the jumper wire and install

the LWCO wiring from LWCO Model 1100-H4 (P/N 100592-01) into the plug of the SCG factory wiring.

How to Test

Shut off fuel supply. Lower water level until water level is BELOW the LWCO. Generate a boiler demand by turning up thermostat. Boiler should not attempt to operate. Increase the water level by filling the system. The boiler should attempt to operate once the water level is above the LWCO.

NOTICE

Ensure the location of the LWCO in the piping will allow for connection of the LWCO wiring harness to the factory wiring of the SCG.

C.Connect system supply and return piping to boiler. See Figures 25 and 26. Maintain minimum ½ inch clearance from hot water piping to combustible materials.

NOTICE

Burnham recommends sizing the system circulator to supply sufficient flow (GPM) to allow a 20°F temperature differential in the system. When sizing the system circulator, the pressure drop of all radiators, baseboard and radiant tubing and all connecting piping must be considered.

D.Install circulator with flanges, gaskets and bolts provided. Circulator harness allows circulator to be mounted on supply or return. Connect harness to circulator and secure any excess conduit.

E.Install supply manifold, pressure/temperature gauge and pressure relief valve.

See Figure 24. Pressure Relief Valve must be installed with spindle in vertical position. Installation of the relief valve must comply with the ASME Boiler and Pressure Vessel Code, Section IV.

WARNING

Pressure relief valve discharge piping must be piped such that the potential of severe burns is eliminated. DO NOT pipe in any area where freezing could occur. DO NOT install any shut-off valves, plugs or caps. Consult Local Codes for proper discharge piping arrangement.

F.Space heating and domestic water heating with Alliance™ water heater. Install Alliance water heater as a separate heating zone. Refer to Alliance Installation, Operating and Service Instructions for additional information.

G.If boiler is used in connection with refrigeration systems, boiler must be installed with chilled medium piped in parallel with the heating boiler using appropriate valves to prevent chilled medium from entering boiler, see Figure 23.

Figure 23: Recommended Piping for Combination

Heating & Cooling (Refrigeration) System

H.If boiler is connected to heating coils located in air handling units where they may be exposed to refrigerated air, boiler piping must be equipped with flow control valves to prevent gravity circulation of boiler water during operation of cooling system.

I.Use a boiler bypass if the boiler is to be operated in a system which has a large volume or excessive radiation where low boiler water temperatures may be encountered (i.e. converted gravity circulation system, etc.).

46

Image 46
Contents SCG 8140705R9-10/08 Price $5.00Important Information Read Carefully Page Table of Contents Dimensions Pre-Installation II. Unpack Boiler Do not drop boiler. Do not bump boiler jacket against floorIII. Venting / Air Intake Piping Required See SectionBurnham Vent System and Air Intake System Components Vent System Components Included with BoilerVent/Air Intake Length Vent Guidelines Due to Removal of an Existing Boiler General GuidelinesInstall Vent Pipe, Burnham Gasketed Vent System Burnham Gasketed Vent Joint DetailVent Piping Recommended Separate Horizontal Vent/Air Intake Installation Alternate Separate Horizontal Vent/Air Intake Installation Page Page Separate Vertical Venting System See Figures 6, 7, 8A, 8B Page Vertical Vent Installation Page Page Vertical Air Intake Piping Install Combination Vent/Air Terminal. See Figure Combination Horizontal Vent System ComponentsInstall Air Intake Piping. See Figures 10 Non-corrosive fasteners must be usedCombination Horizontal Vent/Air Installation SCG-3 thru Page Description Part Number SCG-3 & SCG-4 Combination Vertical Vent System ComponentsGeneral Installation Requirements Pre-Installation ConsiderationsClearances to Combustibles Page Joint Assembly Instructions Inner pipe is always cut 1 longer than the outer pipe Condensate Drains Horizontal Supports Page Fire Stop/Wall Thimble/Support, SC FS Tall Cone Flashing Directly On Roof or CurbPage Horizontal Recommended Separate Horizontal Vent Installation Alternate Separate Horizontal Vent Installation Optional Indoor Air Vent Terminal Installation Install vent piping Optional Separate Horizontal 3 Vent Terminal Installation Optional Separate Horizontal 4 Vent Terminal Installation Page IV. Water Piping and Trim Lwco LocationHow to Wire How to TestSupply Water Manifold Piping Page Page Gas Piping Valves Fully Open Page VI. Electrical Internal Boiler Wiring Schematic Diagram Internal Boiler Wiring Ladder Diagram System Controls and Wiring System Wiring Schematic for Single Zone Space Heating Only Page Circulator Zoned System Wiring Schematic Zone Valve Zoned System Wiring Schematic Page Do not manifold vent pipes together VII. Modular InstallationModular Boiler Water Manifold Sizing Modular Boiler Gas Piping VIII. System Start-up Operating Instructions Ignition Module Terminal CROSS-REFERENCE Operating InstructionsYellow led flame codes Green Led status codes Honeywell Electronic Ignition Troubleshooting Guide Sequence of Operation Check limit Adjust gas input rate to boilerGas Flow Rate in Cubic Feet Per Hour IX. Service Low water cutoff if so equippedSilicone Tubing Assembly Pilot Burner LocationFlue and Burner Cleanout, 1 Burner Differential Pressure Switch Settings Procedure for Measuring Differential Pressure See FigureMain Burners and Firebox This page Left Intentionally Blank Page Page XI. Repair Parts Casting Assembly Page Base Assembly Page Base Enclosure Assembly Page FAN/CANOPY Assembly Page Burner Assemblies Page Control Panel Assembly Page Jacket Parts Miscellaneous Parts Carton Avoid Breathing Fiber Particulates and Dust Service Record Service Record Limited Warranty