Table 2: Vent System Components Included with Boiler

Vent System Components

Part Number

 

 

Gasketed Vent Terminal 3” Horizontal

8110701

(SCG-3 thru SCG-7)

 

Gasketed Vent Terminal 4” Horizontal

8110702

(SCG-8 & SCG 9)

 

Disc Air Intake - 3”

6116045

(SCG-3 & SCG-4)

 

Disc Air Intake - 4”

6116044

(SCG-5 & SCG-6)

 

Air Intake - 5”

6116063

(SCG-7 thru SCG-9)

 

Table 3: Burnham Vent System and Air Intake System Components

Vent System Component

Part Number

Equivalent

Feet of Pipe

 

 

3” Dia. Pipe x 1 Ft

8116296U

1

4” Dia. Pipe x 1 Ft

100176-01

 

3” Dia. Pipe x 3 Ft

8116298U

3

 

 

4” Dia. Pipe x 3 Ft

100177-01

 

 

 

 

3” Dia. Pipe x 5 Ft

8116300U

5

 

 

4” Dia. Pipe x 5 Ft

100178-01

 

 

 

 

3” Dia. Pipe x Adjustable

8116319U

Equal to

 

 

Installed Length

4” Dia. Pipe x Adjustable

100179-01

(1.06 TO 1.64)

3” Dia. 90° Elbow

8116294U

5

4” Dia. 90° Elbow

100180-01

 

3” Dia. 45° Elbow

8116292U

5

4” Dia. 45° Elbow

100181-01

 

 

 

 

3” Dia. Horizontal Drain Tee

8116302U

2

 

 

4” Dia. Horizontal Drain Tee

100182-01

 

 

 

 

3” Dia. Vertical Drain Tee

8116304U

 

 

4” Dia. Vertical Drain Tee

100183-01

 

 

 

 

3” Single Wall Thimble

8116116

---

4” Single Wall Thimble

100184-01

 

3” Double Wall Thimble

8116115

---

4” Double Wall Thimble

100185-01

 

Intake System Components

Equivalent

(Parts by Others)

Feet of Pipe *

 

 

3”, 4”, or 5” ID Pipe x 1 Ft

1

3”, 4”, or 5” ID Pipe x 2 Ft

2

3”, 4”, or 5” ID Pipe x 4 Ft

4

 

 

3”, 4”, or 5” ID Pipe x 5 Ft

5

 

 

3”, or 4” 90° Elbow

5

 

 

3”, or 4” 45° Elbow

5

 

 

5” 90° Elbow

6

 

 

5” 45° Elbow

6

*Equivalent Feet of Pipe Based on Standard 4” Smoke Pipe Design

Table 4: Vent/Air Intake Length

 

3” Air Intake Pipe

4” Air Intake Pipe

5” Air Intake Pipe

3” Vent Pipe

4” Vent Pipe

Model

(Equiv. Ft.)

(Equiv. Ft.)

(Equiv. Ft.)

(Equiv. Ft.)

(Equiv. Ft.)

 

Min.

Max.

Min.

Max.

Min.

Max.

Min.

Max.

Min.

Max.

SCG-3 & SCG-4

8

50

---

---

---

---

8

50

---

---

SCG-5 & SCG-6

---

---

8

50

---

---

8

50

---

---

SCG-7

---

---

---

---

8

50

8

50

---

---

SCG-8 & SCG-9

---

---

---

---

8

40

---

---

8

40

Image 9
Contents 8140705R9-10/08 Price $5.00 SCGImportant Information Read Carefully Page Table of Contents Dimensions Pre-Installation Do not drop boiler. Do not bump boiler jacket against floor II. Unpack BoilerRequired See Section III. Venting / Air Intake PipingVent System Components Included with Boiler Burnham Vent System and Air Intake System ComponentsVent/Air Intake Length General Guidelines Vent Guidelines Due to Removal of an Existing BoilerBurnham Gasketed Vent Joint Detail Install Vent Pipe, Burnham Gasketed Vent SystemVent Piping Recommended Separate Horizontal Vent/Air Intake Installation Alternate Separate Horizontal Vent/Air Intake Installation Page Page Separate Vertical Venting System See Figures 6, 7, 8A, 8B Page Vertical Vent Installation Page Page Vertical Air Intake Piping Combination Horizontal Vent System Components Install Combination Vent/Air Terminal. See FigureNon-corrosive fasteners must be used Install Air Intake Piping. See Figures 10Combination Horizontal Vent/Air Installation SCG-3 thru Page Combination Vertical Vent System Components Description Part Number SCG-3 & SCG-4Pre-Installation Considerations General Installation RequirementsClearances to Combustibles Page Joint Assembly Instructions Inner pipe is always cut 1 longer than the outer pipe Condensate Drains Horizontal Supports Page Tall Cone Flashing Directly On Roof or Curb Fire Stop/Wall Thimble/Support, SC FSPage Horizontal Recommended Separate Horizontal Vent Installation Alternate Separate Horizontal Vent Installation Optional Indoor Air Vent Terminal Installation Install vent piping Optional Separate Horizontal 3 Vent Terminal Installation Optional Separate Horizontal 4 Vent Terminal Installation Page Lwco Location IV. Water Piping and TrimHow to Test How to WireSupply Water Manifold Piping Page Page Gas Piping Valves Fully Open Page VI. Electrical Internal Boiler Wiring Schematic Diagram Internal Boiler Wiring Ladder Diagram System Controls and Wiring System Wiring Schematic for Single Zone Space Heating Only Page Circulator Zoned System Wiring Schematic Zone Valve Zoned System Wiring Schematic Page VII. Modular Installation Do not manifold vent pipes togetherModular Boiler Water Manifold Sizing Modular Boiler Gas Piping VIII. System Start-up Operating Instructions Operating Instructions Ignition Module Terminal CROSS-REFERENCEYellow led flame codes Green Led status codes Honeywell Electronic Ignition Troubleshooting Guide Sequence of Operation Adjust gas input rate to boiler Check limitGas Flow Rate in Cubic Feet Per Hour Low water cutoff if so equipped IX. ServicePilot Burner Location Silicone Tubing AssemblyFlue and Burner Cleanout, 1 Burner Procedure for Measuring Differential Pressure See Figure Differential Pressure Switch SettingsMain Burners and Firebox This page Left Intentionally Blank Page Page XI. Repair Parts Casting Assembly Page Base Assembly Page Base Enclosure Assembly Page FAN/CANOPY Assembly Page Burner Assemblies Page Control Panel Assembly Page Jacket Parts Miscellaneous Parts Carton Avoid Breathing Fiber Particulates and Dust Service Record Service Record Limited Warranty