Blodgett XR8-G manual Standard Control, Operation

Page 18

Operation

Standard Control

OPERATION

Oven Startup

1.Be sure the GAS SHUTOFF SWITCH (13) is in the on position.

2.Turn the POWER SWITCH (1) to the on posi- tion. The HEAT LED (3) lights and the oven preheats to the last used set temperature.

Programming a Bake Cycle

1.Press the TEMP KEY (7). Turn the DIAL (6) to the desired bake temperature.

2.Press the TIME KEY (8). Turn the DIAL (6) to the desired bake time.

3.If steam is desired, press the STEAM KEY (9). Turn the DIAL (6) to the desired steam time. Steam may be programmed for the beginning of the bake cycle for up to two minutes.

4.If you wish to delay the rotation of the convec- tion fan at the beginning of the bake cycle, press the FAN DELAY (10) key. Turn the DIAL

(6) to the desired fan delay time.

5.Press the START/STOP KEY (12) to begin the bake cycle. The oven rack rotates.

During the Bake Cycle

1.To view the remaining bake time, press the TIME KEY (8).

2.To view the actual oven temperature, press the TEMP KEY (7).

3.To inject up to two minutes of steam during the bake cycle, press the STEAM KEY (9).

4.To vent moisture from the oven cavity, press the VENT KEY (11). This manually opens the oven vent until the key is pressed again to close it.

5.To pause a bake cycle at any point, press the START/STOP KEY (12). The cycle will pause until the key is pressed again.

At the End of the Bake Cycle

1.At the end of the bake cycle, an alarm sounds, the display reads DONE and the rack contin- ues to rotate until the door is opened. Press the START/STOP KEY (12) to silence the alarm.

2.Open the door to remove the product.

Oven Shutdown

1.Turn the POWER SWITCH (1) to the off posi- tion.

14

Image 18
Contents XR8-G Avertissement Reputation YOU can Count on Page Table of Contents/Table des Matières Plumbing Specifications -- XR8-G/AA Oven Description and SpecificationsGAS Specifications -- XR8-G/AA IntroductionDelivery and Inspection InstallationDelivery and Location Oven LocationOven Assembly Assembly to StandAssembly to Optional Proofer Ventilation Canadian installationsGeneral export installations Canopy Type Exhaust HoodUtility Connections --- Standards and Codes Gas Connection GAS PipingKPa Manifold Pressure Natural Propane Pressure Regulation and TestingInlet Pressure Natural Propane KPaGAS Hose Restraint Plumbing Connections Electrical SpecificationsPlumbing and Electrical Connections Electrical ConnectionsAdjustments Associated with Initial Installation Initial StartupWhat to do in the event of a power failure Safety InformationSafety Tips General safety tipsSolid State Digital Control Control DescriptionStandard Control OperationGeneral Guidelines for Operating Personnel Operating TipsCleaning the Oven MaintenanceCleaning and Preventative Maintenance Preventative MaintenanceTroubleshooting Guide Possible Causes Suggested RemedyGaz Naturel Gaz Propane Unités US Unités SI Specifications Pour GAZ -- XR8-G/AADescription et Spécifications du Four Spécifications DE Plomberie -- XR8-G/AALivraison et Implantation Livraison ET InspectionImplantation DU Four Montage du Four Assemblage SUR UN StandAssemblage SUR UNE Étuve DE FER- Mentation Optionnelle Avertissement Installation aux États-Unis et au CanadaGénéralités concernant les installations à l’ex- portation Hotte D’ÉVACUATION Type VoûteBranchements de Service --- Normes et Codes Généralités concernant les installations à l’exportationConduit DE GAZ Longeur Dimensions nominales De conduit PiedsBranchement de Gaz ExempleRéglage ET Test DE Pression Pression à l’entrée Gaz Naturel Gaz PropaneKPa Pression au collecteur Gaz Naturel Gaz Propane Retenue DU Tuyau DE GAZ Raccordements de purge Raccordement Électrique et PlomberieRaccordement Plomberie Avertissement Raccordement ÉlectriqueRéglages À Faire Lors DE L’INSTALLA- Tion Initiale Mise en Marche InitialeConseils DE Sécurité UtilisationInformations de Sécurité Que faire en cas de panne de secteurCommande Classique Description DES CommandesUtilisation Consignes Générales à l’Intention des Utilasateurs ConseilsEntretien Maintenance PreventiveMaintenance annuelle Nettoyage et Entretien PréventifGuide de Détection des Pannes Causes Probables SuggestionGuide de Détection des Pannes Insert Wiring Diagram Here Placer Schéma DE Câblage ICI