Blodgett XR8-G manual Plumbing and Electrical Connections, Plumbing Connections

Page 14

Installation

Plumbing and Electrical Connections

PLUMBING CONNECTIONS

WARNING!!

Plumbing connections must comply with applicable sanitary, safety and plumbing codes.

Water Connections

Water supply should meet the following condi- tions. Consult your local water company before installing the oven.

DHardness of 4-6 grains per gallon (100ppm max) D PH of 6.5 to 8.0

D Chlorides less than 30 PPM

1.Connect the cold water supply to the 3/4” MGHT connection on the back of the oven with the water line provided. Supply pressure should be 30 to 75 psi (207 to 517 kPa) when the steam solenoid is open. The water regula- tor on the oven itself must be set to 15 psi (103 kPa) when the steam solenoid is open.

Drain Connections

1.Connect drain line to the 3/4” NPT drain con- nection on the back of the oven.

2.Route the drain line to a floor drain. Allow a 1” air gap between the drain line and the floor drain.

NOTE: When the oven is stacked on a proofer a separate drain line should be installed. If a second drain line is not possible, pro- vide a vent opening in the drain line above the oven drain connection. Be sure to pro- vide enough drop so the oven drain will not flood the proofer cabinet.

ELECTRICAL CONNECTIONS

Wiring diagrams are located in the right bodyside.

This oven is supplied for connection to a 120 volt grounded circuit. The electric motor, indicator lights and related switches are connected through the 6’ electric supply cord found at the rear of the oven.

NOTE: When the oven is installed with a proofer a separate 120 volt grounded circuit will be required.

WARNING!!

This appliance is equipped with three prong grounding type plug for your protection against shock hazard and should be plugged directly into a properly grounded three prong receptacle. DO NOT cut or remove the grounding prong from this plug.

THE BLODGETT OVEN COMPANY CANNOT AS- SUME RESPONSIBILITY FOR LOSS OR DAMAGE SUFFERED AS A RESULT OF IMPROPER INSTAL- LATION.

ELECTRICAL SPECIFICATIONS

Model

Hz

Volts

Phase

Amps

Electrical Connection

 

 

 

 

 

(minimum size)

 

 

 

 

 

 

XR8-G

60

120

1

5

Cord set provided

 

 

 

 

 

 

10

Image 14
Contents XR8-G Avertissement Reputation YOU can Count on Page Table of Contents/Table des Matières Plumbing Specifications -- XR8-G/AA Oven Description and SpecificationsGAS Specifications -- XR8-G/AA IntroductionDelivery and Inspection InstallationDelivery and Location Oven LocationAssembly to Optional Proofer Oven AssemblyAssembly to Stand Ventilation Canadian installationsGeneral export installations Canopy Type Exhaust HoodUtility Connections --- Standards and Codes Gas Connection GAS PipingKPa Manifold Pressure Natural Propane Pressure Regulation and TestingInlet Pressure Natural Propane KPaGAS Hose Restraint Plumbing Connections Electrical SpecificationsPlumbing and Electrical Connections Electrical ConnectionsAdjustments Associated with Initial Installation Initial StartupWhat to do in the event of a power failure Safety InformationSafety Tips General safety tipsSolid State Digital Control Control DescriptionStandard Control OperationGeneral Guidelines for Operating Personnel Operating TipsCleaning the Oven MaintenanceCleaning and Preventative Maintenance Preventative MaintenanceTroubleshooting Guide Possible Causes Suggested RemedyGaz Naturel Gaz Propane Unités US Unités SI Specifications Pour GAZ -- XR8-G/AADescription et Spécifications du Four Spécifications DE Plomberie -- XR8-G/AAImplantation DU Four Livraison et ImplantationLivraison ET Inspection Assemblage SUR UNE Étuve DE FER- Mentation Optionnelle Montage du FourAssemblage SUR UN Stand Avertissement Installation aux États-Unis et au CanadaGénéralités concernant les installations à l’ex- portation Hotte D’ÉVACUATION Type VoûteBranchements de Service --- Normes et Codes Généralités concernant les installations à l’exportationConduit DE GAZ Longeur Dimensions nominales De conduit PiedsBranchement de Gaz ExempleKPa Pression au collecteur Gaz Naturel Gaz Propane Réglage ET Test DE PressionPression à l’entrée Gaz Naturel Gaz Propane Retenue DU Tuyau DE GAZ Raccordements de purge Raccordement Électrique et PlomberieRaccordement Plomberie Avertissement Raccordement ÉlectriqueRéglages À Faire Lors DE L’INSTALLA- Tion Initiale Mise en Marche InitialeConseils DE Sécurité UtilisationInformations de Sécurité Que faire en cas de panne de secteurCommande Classique Description DES CommandesUtilisation Consignes Générales à l’Intention des Utilasateurs ConseilsEntretien Maintenance PreventiveMaintenance annuelle Nettoyage et Entretien PréventifGuide de Détection des Pannes Causes Probables SuggestionGuide de Détection des Pannes Insert Wiring Diagram Here Placer Schéma DE Câblage ICI