Battery Rack Assembly and Installation Manual 9
Rack Assembly

Assembling the bottom section

The bottom section of the rack will contain shelves #3 and #4.
1. Bolt Cross Bar #1 to Bottom Side Subassembly #1 at hole position #2 (from front) on the
LOWER horizontal support of the Subassembly. Use (1) 3/8-16 x 1” bolt and related hardware:
(2) 3/8 washers and (1) 3/8 KEPS nut.
2. Bolt Cross Bar #2 to Bottom Side Subassembly #1 at hole position #6 (from front) on the
LOWER horizontal support of the Subassembly. Use (1) 3/8-16 x 1” bolt and related hardware:
(2) 3/8 washers and (1) 3/8 KEPS nut.
3
3
333/8
3
3/8-16 x 1” Bolt
(812-0723)
3/8 Washers
(812-2030)
3/8 KEPS Nut
(812-3101)
Bottom Side Subassembly #1
(870-1658A)
Cross Bar #1
(870-3698)
Hole Position #2
from Front
Bottom Side Subassembly #1
Cross Bar #1
Cross Bar #2
(870-3698)
Hole Position #6
from Front