Rack Assembly

3.Using specified cable, connect the open BAT 2+ terminal in Terminal Block #2 to the open positive (+) terminal on Battery #33. Before making connections, apply ONE cable boot. If lug sizes are different, apply boot to the cable end with the SMALLER lug.

At Terminal Block #2: Connect the lug on the cable end WITHOUT the boot to the open BAT 2+ terminal. Secure lug to stud with preset washer and nut. Snake cable end WITH the boot between centrally located rails until it reaches Battery #33.

At Battery #33: Connect the lug on the cable end WITH the boot to the open positive (+) terminal on Battery #33. Snap the boot over the connected lug/terminal. Use zip ties as needed to relieve cable strain.

36

40

shelf-to-shelf

to Battery #41

35

39

 

34

38

 

33

37

 

Rack #2, Top Shelf

 

Terminal Block #2

 

 

+

-

 

Battery Rack Assembly and Installation Manual

31

Page 37
Image 37
American Power Conversion 400kW1MW installation manual Rack #2, Top Shelf Terminal Block #2