Contents
Battery Racks for 400kW-1MW UPS Systems
Assembly and Installation Manual
Battery Rack Assembly and Installation Manual
Contents
Rack Assembly
Appendix C Employing Sidecars
Battery Rack Assembly and Installation Manual
Safety
Safety warnings
Safety precautions
Additional considerations
Specifications
Rack/battery options
Weights and dimensions
Shipping and Receiving
Shipping
Receiving
Placement
Positioning
Handling
Installation Site
Installation considerations
Installation equipment
Torque specifications
Parts List
APC P/N
Battery Cabling
Rack Assembly
Assembling the bottom section
Refer to graphic in below
Assembling the top section
Top Side Subassembly #2 870-1657A Bottom Side Subassembly #2
Top Side Subassembly #1 Cross Bar #6 Top Side Subassembly #2
Connection
Stabilizing the rack
Accessing your wiring diagrams
Anchoring the rack optional
Numbering the batteries
Positioning rails on shelves
Addressing the bottom shelf
Wiring the batteries
Rack Assembly
Stud Terminal
Addressing the third shelf
Addressing the second shelf
Addressing the top shelf
Shelf-to-shelf wiring
Assembling the second rack
Labelling the terminal blocks
Employing sidecars to support separated racks
Connecting terminal blocks to battery breakers
To Battery Breaker #1 BAT 1- terminal
Connecting terminal blocks to batteries
Rack #1, Top Shelf Terminal Block #1
Shelf-to-shelf From Battery #24
Rack #2, Top Shelf Terminal Block #2
Shelf-to-shelf From Battery #56
Reattaching terminal block covers
Applying warning labels
Grounding the racks
Glossary
APC
Appendix a Battery Wiring Style E
Style E, rack #1, shelf #1 top
Style E, rack #1, shelf #2
Style E, rack #1, shelf #3
Style E, rack #1, shelf #4 bottom
Style E, rack #2, shelf #1 top
Style E, rack #2, shelf #2
Style E, rack #2, shelf #3
Style E, rack #2, shelf #4 bottom
Appendix B Battery Cabling Kits
References for Power battery cables
References for Fiamm battery cables
Appendix C Employing Sidecars
Sidecar overview
Positioning and accessing the sidecar
Connecting terminal blocks to sidecars
To BAT
To BAT 2+
Appendix C Employing Sidecars
Connecting sidecars to battery breakers
At the Sidecar
BAT 2+ Top
BAT
BAT 1+ Top
Battery Rack Assembly and Installation Manual
Battery Rack Assembly and Installation Manual
Battery Rack Assembly and Installation Manual
APC Warranty on Batteries
APC Worldwide Customer Support
990-4194A