Eaton Electrical SC200 manual Pre-Power-Up Check, Checklist

Models: SC200

1 78
Download 78 pages 21.25 Kb
Page 35
Image 35

Pre-Power-Up Check

Pre-Power-Up Check

Use the checklist below to complete initial checks before progressing further.

Checklist …

…

…

All AC and DC cabling is installed

All cabling is neat and correctly insulated

DC battery and load cabling has the correct polarity

…All panels are in place and all empty rectifier slots are covered with blanking panels

…The AC supply to the power system is switched OFF

…All circuit breakers at the front of the power system are switched OFF

…Batteries (if fitted) are isolated from the power system

Copyright © 2005-2006 Eaton Corporation. All Rights Reserved.

4-3

IPN 997-00012-41D December 2006

 

Page 35
Image 35
Eaton Electrical SC200 manual Pre-Power-Up Check, Checklist