1/8 in. Plugged Tap
6 in. Trap
Supply Gas Line
From
Gas
Supply
Ground Joint Union
Gas Cock
To
Controls

Installation of Gas Piping

IMPORTANT

All gas piping must be installed in accordance with the latest edition of the National Fuel Gas Code ANSI/Z223.1 and any local codes that may

1.Determine the Supply Gas Requirements

The unit’s nameplate states the requirements for the gas being supplied to the unit.

Minimum gas pressure for maximum output

apply. In Canada, the equipment shall be installed in accordance with the Installation Code for Gas Burning Appliances and Equipment (CGA B149) and Provincial Regulations for the class. Authorities having jurisdiction should be consulted before installations are made.

IMPORTANT

All piping should be clean and free of any foreign material. Foreign material entering the gas train can cause damage.

Warning

MAX BTU/HR

 

 

BTU/H MAX

 

 

 

 

 

 

 

 

 

 

NORMAL MANIFOLD

 

 

PRESSURE

 

“W.C.

PRESSION DÕADMISSION

 

 

 

NORMALE

 

 

 

 

 

 

 

 

 

 

MIN GAS

 

 

PRESSURE

 

“W.C.

PRESSION DE GAZ

 

 

 

 

 

 

 

 

 

 

 

 

 

“W.C.

 

 

 

 

 

 

 

 

TYPE OF GAS

 

 

NATURE DU GAZ

 

 

 

 

 

 

 

 

 

AGAINST

EQUIPPED FOR

 

 

 

 

SCFM

 

CONCU POUR

 

 

CONTE

 

 

 

 

MIN BTU/HR

BTU/H MIN

MIN GAS PRESSURE

FOR MAX OUTPUT

PRESSION DE GAZ MIN

POUR PUISSANCE MAX

MAX GAS

PRESSURE“W.C.

PRESSION DE GAZ MAX

PSI

DESIGN ΔT

ΔT NORMALE

F

EXTERNAL STATIC PRESSURE

“W.C.

PRESSION STATIQUE EXTERIEURE

All components of this or any other gas fired heating unit must be leak tested prior to placing the unit into operation. A soap and water solution should be used to perform this test. NEVER test for gas leaks with an open flame.

IMPORTANT

Do NOT connect the unit to gas types other than what is specified and do NOT connect the unit to gas pressures that are outside of the pressure range shown on the label.

Warning

When leak testing pressures equal to or less than 14 in. wg (3.5 kPa), first close the field-installed shutoff valve to isolate the unit from the gas supply line.

Note

When connecting the gas supply, the length of the run must be considered in determining the pipe size to avoid excessive pressure drop. Refer to a Gas Engineer’s Handbook for gas pipe capacities.

Note

Each furnace has a single 3/4-inch connection.

®

Type of gas

Maximum gas pressure

Indirect Gas Nameplate

2. Install Additional Regulator if Required

When the supply gas pressure exceeds the maximum gas pressure shown on the unit’s nameplate, an

additional regulator (by others) is required to reduce

the pressure. The

 

 

 

 

Supply Gas Pressure Range

regulator must have a

(in. wg)

listed leak limiting device

 

 

Minimum

Maximum

or it must be

 

vented to the

Natural

6

14

 

 

 

LP

10

14

outdoors.

3. Connect the Supply Gas Line

A manual shut off valve (gas cock), 1/8 inch plugged test port and 6 inch drip leg must be installed prior to the gas train. The valve and the test port must be accessible for the connection of a test gauge. Supply gas

connections must be made by

a qualified installer and are not

furnished by manufacturer.

4. Test the System for Leaks

Check both the supply lines and the factory piping for leaks. Apply a soap and water solution to all piping and watch for bubbling which indicates a leak.

Warning

NEVER test for a gas leak with an open flame.

Warning

The factory piping has been checked for leaks, but should be rechecked due to shipping and installation.

Model IG / IGX Make-Up Air 17

Page 17
Image 17
Greenheck Fan 470656 manual Installation of Gas Piping, Determine the Supply Gas Requirements, Connect the Supply Gas Line