Greenheck Fan 470656 Table of Contents, Clearance to Combustibles / Service Clearances, Start-Up

Models: 470656

1 72
Download 72 pages 41.99 Kb
Page 3
Image 3
Indirect Gas Fired Unit Installations

3.After storage period, purge grease before putting fan into service.

Indirect Gas Fired Unit Installations

Units are listed for installation in the United States and Canada.

Installation of gas fired duct furnaces must conform with local building codes. In the absence of local codes, installation must conform to the National Fuel Gas code, ANSI Z223.1 or in Canada, CAN/ CGA-B149 installation codes.

All electrical wiring must be in accordance with the regulation of the National Electrical Code, ANSI/ NFPA 70.

Unit is approved for installation downstream from refrigeration units. In these conditions, condensate could form in the duct furnace and provision must be made to dispose of the condensate.

Table of Contents

Installation

Clearance to Combustibles/Service Clearances. 3

Indoor Unit

 

 

4

Unit Arrangement DB / HZ

. . 4-5

Roof Mounted Unit – Arrangement DBC. .

. . 5-6

Optional Evaporative Cooling Module.. . .

.

.

7

Venting – Outdoor

.

.

. 7

Indoor, All Units

 

 

8

Standard Indoor . . . . . . . . . . .9

Concentric, General

.

.

.10

Concentric, Horizontal

.

10-11

Concentric, Vertical

 

11-12

Two Pipe, Horizontal

 

 

13

Two Pipe, Vertical

.

.

.14

Electrical Wiring . . . . . . . . . . . . . 15-16

Gas Piping. . . . . . . . . . . . . . . . .17

Optional Evaporative Cooler Piping . . . .

 

18-19

Optional Water Wizard™

.

19-20

Optional Direct Expansion (DX) Coil Piping. 20-21

Optional Chilled Water Coil Piping

 

 

22

Optional Building Pressure Control. . . .

.

.

.22

Start-Up

Blower. . . . . . . . . . . . . . . . . 23-24

Furnace – All Units

.

. 25

Single Stage

 

25

2:1 Staged. . . . . . . . . . . . 26

8:1 Staged. . . . . . . . . . . 26-28

2:1 Modulation

 

29

4:1 Modulation

30-31

Optional Economizer . . . . . . . . . . . . 32

Optional Evaporative Cooling

 

33

Optional Water Wizard™

34-35

Operation

 

 

Optional Water Wizard™

.

.35

Optional VAV Units

.

. 36

Optional Recirculating Units

 

37

®

Sequence of Operation, Furnace –

2:1 Staged . . . . . . . . . . . . . . .38 2:1 Modulation. . . . . . . . . . . . 39-40

Operation of Controller –

4:1 Modulation/8:1 Staged Controller. . 40-41 Sequence of Operation, Furnace –

4:1 Modulation. . . . . . . . . . . . 41-42 8:1 Staged . . . . . . . . . . . . . 43-44 Ignition Controller. . . . . . . . . . . . . .44 Economizer. . . . . . . . . . . . . . . . 45

Troubleshooting

Blower. . . . . . . . . . . . . . . . . . 46

Motor Over Amps

. . . .

.

.47

Insufficient / Too Much Airflow

. . .

 

 

48

Excessive Noise / Vibration. . . .

. . .

.

.

.49

Furnace – Staged

. . . .

.

.50

2:1 Modulation

. .

 

 

51

4:1 Modulation

 

 

52-53

8:1 Staged. . . . . . . . . . . 54-55

Optional Evaporative Cooling

. .

 

 

56

Optional Water Wizard™

. . .

.

.

.57

Maintenance

Routine . . . . . . . . . . . . . . . . 58-59 Fall. . . . . . . . . . . . . . . . . . 60-61

Reference

Vent Connections . . . . . . . . . . . . . .62

Model IG – Single or 2 Stage

.

.

63

8:1 Staged . . . . . . . . . . . .64

2:1 Modulation

.

.

65

4:1 Modulation

.

.

66

Model IGX – Blower Control Center

 

 

67

Single or 2 Stage

.

.

68

8:1 Staged . . . . . . . . . . . .68

2:1 Modulation

.

.

69

4:1 Modulation

.

.

69

Performance Table . . . . . . . . . . . . . 70

Start-Up Checklist

 

 

71

Maintenance Log . . . . . . . . . . Backcover Warranty . . . . . . . . . . . . . . Backcover

Clearance to Combustibles / Service Clearances

 

Floor

Top

Sides

Ends

 

 

 

 

 

Indirect Fired

0 inches

0 inches

0 inches

0 inches

Units*

(0 mm)

(0 mm)

(0 mm)

(0 mm)

Clearance to combustibles is defined as the minimum distance required between the heater and adjacent combustible surfaces to ensure the adjacent surface’s temperature does not exceed 90 degrees above the ambient temperature.

*Reference venting guidelines for combustion blower clearances.

Recommended Minimum Service Clearances

Housing 32

42 inches (1067 mm) on the

and less

controls side of the unit

Clearances for component removal (such as evaporative cooler media) should be 6 in. wider than the width of the module itself.

Model IG / IGX Make-Up Air 3

Page 3
Image 3
Greenheck Fan 470656 Table of Contents, Clearance to Combustibles / Service Clearances, Installation, Start-Up, Operation