Completing the installation

CAUTION:

Hazardous energy is present when the blade server is connected to the power source. Always replace the blade cover before installing the blade server.

9.Reinsert the blade server into the bay in the BladeCenter unit.

10.Turn on the blade server.

11.Start the blade server Configuration/Setup Utility program and set configuration parameters as needed (see “Using the Configuration/Setup Utility program” on page 11 for information).

Completing the installation

To complete the installation, perform the following tasks. Instructions for each task are in the following sections.

1.Reinstall the blade server bezel assembly, if you removed it (see “Installing the blade server bezel assembly”).

Attention: To help ensure proper cooling and system reliability, the air baffle must be correctly positioned and fully seated.

2.Close the blade server cover, unless you installed the SCSI storage expansion unit option (see “Closing the blade server cover” on page 63).

Statement 21:

CAUTION:

Hazardous energy is present when the blade server is connected to the power source. Always replace the blade cover before installing the blade server.

3.Reinstall the blade server into the BladeCenter unit (see “Installing the blade server in the BladeCenter unit” on page 65).

4.Turn on the blade server (see “Turning on the blade server” on page 6).

Note: Reinstall the bezel assembly on the BladeCenter T unit after you have finished turning on the blades. However, if you installed an option such as a PCI I/O Expansion Unit with PCI adapters that require cables, you will not be able to install the bezel assembly, which contains an air filter for the

BladeCenter T unit. If you cannot install the bezel assembly, a filter must be provided on the rack. See the IBM Eserver BladeCenter T Planning and

Installation Guide for information about installing an air filter on the rack (you can obtain the planning guide from http://www.ibm.com/pc/support/).

5.For certain options, run the blade server Configuration/Setup Utility program (see “Updating your blade server configuration” on page 67).

Note: If you have just connected the power cords of your BladeCenter unit to electrical outlets, you will have to wait until the power-on LED on the blade server flashes slowly before pressing the power-control button on a blade server.

Installing the blade server bezel assembly

Complete the following steps to install the blade server bezel assembly.