UPS SYSTEM INSTALLATION

Screw from Kit

Bracket from Kit

ISBM

Section Top

Screw from Kit

Screw from Kit

Screw from Kit

 

 

Back

UPM

Bracket from Kit

 

Section Top

 

 

 

ISBM

UPM

 

Section Top

Section Top

Front

Top View Front Bracket

Bracket from Kit ISBM Section Base

Top View Rear Bracket

UPM Section Base

Front View Base Bracket

Screw from Kit

Screw from Kit

Figure 4-7. ISBM Section to UPM Section Joining Brackets

4.4Electrically Connecting the Sections

1.Unfasten the front door latch and swing the door open (see Figure 4-1on page 4−2).

2.Remove the door. Remove the retaining screw located inside the door at the bottom hinge pivot point, then lift the door off. Retain the hardware for later use.

3.Remove the screws securing the ISBM section right bottom internal safety shield panel and remove the panel to gain access to the internal input, output, and battery terminals. Retain the hardware for later use.

NOTE AC and DC input intercabinet power wiring harnesses are supplied coiled and secured in the UPM wireway on the left side of the UPM section (see Figure 4-6on page 4−7).

4.Locate the AC and DC input intercabinet power wiring harnesses (long cables labeled xG1, xG2, and xG3). Remove wire ties as necessary and uncoil the cables.

5.Locate the 1G1, 1G2, 2G1, 2G2, 3G1, and 3G2 power wiring harnesses. Route these harnesses through the wiring access in the right side panel of the ISBM section to the AC Input to UPMs terminals. See Figure 4-8on page 4−11 for terminal locations.

4−8

EATON Powerware® 9395 UPS (1000–1100 kVA) Installation and Operation Manual S 164201764 Rev 1 www.powerware.com

Page 52
Image 52
Powerware 10001100 kVA Electrically Connecting the Sections, Screw from Kit Bracket from Kit, Section Top Screw from Kit