UPS SYSTEM INSTALLATION
NOTE Two cable lugs will be connected to each terminal stud. When connecting the cable lugs, install the first lug on the stud with the raised barrel portion facing the back of the cabinet. Install the second lug with the raised barrel portion facing the front of the cabinet.
6.Locate the intercabinet wiring terminal hardware kit packed on the bottom right side of the ISBM section.
7.Using hardware from the intercabinet wiring terminal hardware kit (see Table
NOTE In Step 8, route the wiring harnesses in the area as shown in Figure
8.Locate the 1G3, 2G3, and 3G3 power wiring harnesses. Route these harnesses through the wiring access in the right side panel of the ISBM section to the DC Input to UPMs terminals. See Figure
NOTE When connecting the UPM battery cables, verify the cables are connected to the correct terminals .
9.Using hardware from the intercabinet wiring terminal hardware kit (see Table
NOTE AC output intercabinet power wiring harnesses are supplied attached to the interior left side panel of the UPM section (see Figure
10.Locate the 1G4, 1G5, 2G4, 2G5, 3G4, and 3G5 power wiring harnesses. Remove the front two columns of wire ties securing the cables to facilitate routing cables to the AC Output from UPMs terminals. See Figure
NOTE Two cable lugs will be connected to each terminal stud. When connecting the cable lugs, install the first lug on the stud with the raised barrel portion facing the back of the cabinet. Install the second lug with the raised barrel portion facing the front of the cabinet.
11.Using hardware from the intercabinet wiring terminal hardware kit (see
Table
12.Install the remaining hardware (three washers, conical washers, and nuts) onto the AC Input to UPMs terminals designated for the four UPM model and secure the hardware (see Figure
EATON Powerware® 9395 UPS | 4−9 |