UPS SYSTEM INSTALLATION
EATON Powerware® 9395 UPS (1000–1100 kVA) Installation and Operation Manual S 164201764 Rev 1 www.powerware.com
4−38
Installation Checklist
-All packing materials and restraints have been removed from each cabinet.
-Each cabinet in the UPS system is placed in its installed location.
-Joining brackets are installed between the ISBM and UPM sections.
-Intercabinet power wiring is installed between the ISBM and UPM sections.
-Intercabinet interface wiring is installed between the ISBM and UPM sections.
-A cabinet grounding/mounting kit is installed between the ISBM and UPM sections.
-All conduits and cables are properly routed to the UPS and any ancillary cabinets.
-All power cables are properly sized and terminated.
-Neutral conductors are installed or bonded to ground per requirements.
-Battery cables are terminated on E4 (+) and E5 (–).
-Battery aux contact signal wiring is connected from the UPS to the battery disconnect.
-Battery shunt trip signal wiring is connected from the UPS to the battery disconnect. (OPTIONAL)
-LAN and telephone drops are installed.
-All telephone and LAN connections have been completed.
-A ground conductor is properly installed.
-Air conditioning equipment is installed and operating correctly.
-The area around the installed UPS system is clean and dust-free. (It is recommended that the UPS be installed on a
level floor suitable for computer or electronic equipment.)
-Adequate workspace exists around the UPS and other cabinets.
-Adequate lighting is provided around all UPS equipment.
-A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
-The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet.
-The normally−closed (NC) Emergency Power−off contact (pins 1 and 2 on TB1) is jumpered if not used.
-Alarm relays and building alarms are wired appropriately. (OPTIONAL)
-A remote battery disconnect is mounted in its installed location and its wiring is terminated inside the UPS.
(OPTIONAL)
-Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (OPTIONAL)
-The debris shields covering the UPS cabinet ventilation grills are removed.
-Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.