UPS SYSTEM INSTALLATION

Distributed Bypass Installation Checklist

-Each cabinet in the distributed bypass system is placed in its installed location.

-All conduits and cables are properly routed to the UPS cabinets and to the tie cabinet or distribution panel.

-All power cables are properly sized and terminated.

-Neutral conductors are installed or bonded to ground as per requirements.

-A ground conductor is properly installed.

-Controller Area Network (CAN) wiring between the UPS cabinets is properly installed.

-Pull−chain wiring between the UPS cabinets is properly installed.

-Adequate workspace exists around the UPS cabinets, the tie cabinet, and other cabinets.

-Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.

EATON Powerware® 9395 UPS (1000–1100 kVA) Installation and Operation Manual S 164201764 Rev 1 www.powerware.com