INSTALLATION
17.If installing communication functions, install the wiring for the Alarm Relay and Building Alarms connections. For more information, see
18.Start up the host equipment. Refer to the user’s guide for the host equipment for startup instructions.
19.Activate the reset switch on the bottom of the electronics module: hold the switch for 10 seconds or until the display (if installed) turns off, then release the switch.
20.Verify that the Power LED on the Power Xpert Gateway Series 1000 Card illuminates (see Figure 13).
Display option only. Verify that the display on the front of the electronics module also activates. Press any button to display the mimic screen.
Power LED
Figure 13. Power LED on the Power Xpert Gateway Series 1000 Card
21.Conduit Box option only. Reinstall the top plate on the left conduit box.
22.If installing network connections, proceed to Step 24. Otherwise, continue to the following step.
23.Conduit Box option only. If a right conduit box is installed, reinstall the top plate on the right conduit box.
24.Continue to the following section,
24 EATON Powerware® Energy Management System (EMS) Upgrade Kit User’s Guide S 164201724 Rev 1 www.powerware.com