Installation
Conduit holes/knockouts
For maximum safety, run AC, DC, and communication wires in separate conduits.
Front of Wiring Box
Left side |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Right side |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| ||
|
|
|
|
|
|
|
|
| 1.9 cm (3/4”) Threaded | |||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
| Conduit Holes | |||||||||||||||||||
|
| 1.9 cm (3/4”) or 2.5 cm (1”) Knockouts, | ||||||||||||||||||||||||||||
|
|
|
|
|
|
| also on back of Wiring Box | |||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Back of Wiring Box | AC/DC Disconnect Switch |
Figure 2-5 Knockout Locations on Bottom of Wiring Box
WARNING: Shock hazard
Check for existing electrical or plumbing prior to drilling holes in the walls.
Planning AC Wire Routing
AC connections include all the wires and connectors between the GT Inverter AC terminals and the main utility service panel.
Planning DC Wire Routing