OPERATING PROCEDURE

Fan and Heater

 

 

Adjusting the vaporizer coil on a liquid propane model. The top photo shows

the setting in, and the bottom photo shows the coil out.

Adjusting The Vaporizor

1.Vaporizer should be adjusted so the vapor pipetrain runs warm to the touch (100°-120°F).

2.Loosen 5/16" bolt on adjust- ment bracket.

3.Swivel vaporizer away from flame if running too hot, closer to flame if too cold.

4.Move vaporizer only 1" at a time and allow a few minutes for tem perature to equalize.

5.Tighten 5/16" bolt and watch heater run for several minutes to verify adjustment.

Running The Dryer

The display will indicate "FLAME" when flame is sensed. If no flame is sensed, the "FLAME" message will be off. The display indicates what part of the cycle it is in. If the unit is a hi-lo dryer, the display will indicate whether it is in the "HI- FLAME" or "LO-FLAME" part of the cycle. (See "programming set points" page 21 for setting the hi-lo flame temperature). If the tempera- ture is above the high temperature set- ting,theflamewillbeoff,the"FLAME" message will be out and the display will be flashing "OFF-CYCLE".

If the flame is shut off because of the humidity sensor (humidistat), the display flashes "OFF-CYCLE HUMIDISTAT".

42

Image 42
Contents Service Manual Page Table of Contents Roof Damage Warning and Disclaimer Roof WARNING, Operation & SafetySafety Alert Symbol Proper Use of ProductSafety Power WarningFuel Warning Page Vane Axial Fans Proper Installation of the Ground Rod FAN InstallationPreviously Installed Units Machine to Earth GroundTest Station FAN Specifications RPM Vane Axial FanFAN FAN Troubleshooting Fan Troubleshooting ChartTroubleshooting Fan Control CircuitPush Start Button, Nothing Happens FAN Wiring and Schematic Volt 1 Phase 15 HPMotors with Regreasing FAN ServiceLubricant Grease in motor bearings14 1HP Hub Bolt Torque Requirement for Fan Blades84 ft. lbs. Trantorque 18-1.5HPCentrifugal FAN Service Guide RPM FAN RPM FAN Specifications 150 200 100 FAN Schematic and Wiring Volt 1 Phase 15 HP MarathonSchematic Wiring Diagram Procedure LubricationRelubrication Intervals 15HP 3500RPM fans 16ft. lbs. Browning 29ft. lbs. BrowningGas Heater Service Guide Heater Installation Bin ConfigurationOperating Temperature Table Disconnectand LOCK-OUT Power Before Servicing Heater Replacing HF-7100 Board with HF-7318High Temperature Heater Specifications Low Temperature Heater SpecificationsVane Axial GAS Heater Specifications BTUs per Gauge Pressure PSI Propane Models ApproximateBTUs Gauge Pressure PSI Natural Gas Models Approximate CHI-TOWN GAS Heater Specifications Low & Medium Temperature ModelsCHI-TOWN Heater Specifications High TemperatureMED Temperature Btus Per Gauge Pressure Psi Natural Gas Models ApproximateDownwind Heater Specifications Centrifugal Heater SpecificationsAir Pressure Switch Temperature Sensor Box Installation Transition Hi-limit InstallationHeater Unit Wiring Secondary Heater UnitInstalling Optional Humidity Sensor Figure aOperating Procedure Power UpNormal Operating Displays With Heater Not Running Setting Gas Pressure Starting The DryerOperating Procedure AIR Pressure Switch Adjusting the Air Pressure SwitchAdjusting The Vaporizor Running The DryerProgramming Set Points Run Hours Display Drying Grain Hours To Shutdown ModeProgramming Hours To Shutdown Multiple Heater NotesModulating Valve Operation Amount of gas used by the heaterFactory Configuration Configuration Dip Switches Normally DoneAt GSI Multiple Heater Error Conditions Error ConditionsLimit Switches Misc Error NumbersHeater Service Wiring Diagram Turn Control Power on dryer to the off position Programing Instructions for Series 2000 Heater+18% Programmer Hook UpHeater Electrical Installation Heater Electrical Installation 230V FansConnect power cord to fan control box Plenum Thermostat Mounting Transition HI-LIMIT InstallationMount the housing to the bin Sidewall to seal To the right sideAnnual Heater Inspection Run 2 wires 18 gage between master and slave unit For Units Using HF-7318 Control BoardInstallation For Standard Units FAN PartsWiring Schematic Standard Heater Wiring Standard Heater Schematic TROUBLE-SHOOTING Flow Chart HousingTrouble Shooting Chart 7528% 352%$%/&$86Fan and Heater Gas Heaters Deluxe Heater Wiring Deluxe Heater Schematic Heaters 2ND Heater Installation Installation Standard UnitsInstallation HI-LO Units Smart Board Standard Heaters not HI-LO fireHI-LO Fire Heater Troubleshooting Chart Light IdentificationDescription Fan And Heater Downwind Heat Adjustment Procedure For Heaters Manufactured afterGAS Heaters 2ND Heater Installation Wiring Schematic GAS Heaters Time Delay Reset Electrical CHECK-OUT ChartPurge Delay Flame Probe2ND Heater Installation PRE-1990 GAS Heaters Heater Wiring Diagram Heater Schematic Vane Axial LP HeaterVane Axial Vapor Heater Downwind LP Heater Downwind Vapor Heater Lo-Fire Downwind Heater Miscellaneous Information Flame Detector KIT Installation 1991-1993PNEG-286 Flame Detector Kit InstallationPart Number HF-7136 1994-1995PNEG-286 Flame Detector Kit Installation PRESENTPNEG-286 Application InstallationSELF-OPERATED Modulating Valves OperationBypass Orifice Selection Orifice Sizes in Kit Number PLG14A-600RRepairs and Replacement AdjustmentCheckout Procedure Replacement PartsFENWAL-SERIES Installation InstructionsManual Reset SeriesElectrode Application SpecificationsFlame Sensing Control Board CommentsPolarity Check Fan and Heater Control BoardSystem Checks Initial OperationFENWAL-SERIES Safety Checks Repair and ReplacementsWARRANTY/SERVICE Notes Limited Warranty StatementTwisto Says Motor Capacitor Chart Page 1004 E. Illinois St Assumption, IL Phone Fax February