3 General venting (continued)

Install vent and combustion air piping

￿DANGER The Knight wall mount boiler must be vented and supplied with combustion and

ventilation air as described in this section. Ensure the vent and air piping and the combustion air supply comply with these instructions regarding vent system, air system, and combustion air quality. See also Section 1 of this manual.

Inspect finished vent and air piping thoroughly to ensure all are airtight and comply with the instructions provided and with all requirements of applicable codes.

Failure to provide a properly installed vent and air system will cause severe personal injury or death.

The Knight wall mount boiler vent and air piping can be installed through the roof or through a sidewall. Follow the procedures in this manual for the method chosen. Refer to the information in this manual to determine acceptable vent and air piping length.

You may use any of the vent/air piping methods covered in this manual. Do not attempt to install the Knight wall mount boiler using any other means.

You must also install air piping from outside to the boiler air intake adapter unless following the Optional Room Air instructions on page 18 of this manual. The resultant installation is direct vent (sealed combustion).

Air intake/vent connections

￿WARNING

￿WARNING

NOTICE

This appliance requires a special venting system. Use only approved stainless steel, PVC, CPVC or polypropylene pipe and fittings listed in Tables 3D, 3E, and 3G for vent pipe, and fittings. Failure to comply could result in severe personal injury, death, or substantial property damage.

DO NOT mix components from different systems. The vent system could fail, causing leakage of flue products into the living space. Mixing of venting materials will void the warranty and certification of the appliance.

Installation must comply with local requirements and with the National Fuel Gas Code, ANSI Z223.1 for U.S. installations or CSA B149.1 for Canadian installations.

1.Combustion Air Intake Connector (FIG. 3-6) - Used to provide combustion air directly to the unit from outdoors. A fitting is provided on the unit for final connection. Combustion air piping must be supported per guidelines listed in the National Mechanical Code, Section 305, Table 305.4 or as local codes dictate.

2.Vent Connector (FIG.'s 3-7 thru 3-9) - Used to provide a passageway for conveying combustion gases to the outside. A transition fitting is provided on the unit for final connection. Vent piping must be supported per the National Building Code, Section 305, Table 305.4 or as local codes dictate.

Figure 3-6Near Boiler Air Piping

AIR

￿WARNING

￿CAUTION NOTICE

For closet and alcove installations, CPVC, polypropylene or stainless steel material MUST BE used in a closet/alcove structure. Failure to follow this warning could result in fire, personal injury, or death.

Improper installation of venting systems may result in injury or death.

Follow the instructions in Section 1, page 11 of this manual when removing a boiler from an existing vent system.

￿WARNING Do not connect any other appliance to the vent pipe or multiple boilers to a

common vent pipe. Failure to comply could result in severe personal injury, death, or substantial property damage.

15

Image 15
Contents Models 51 Contents Please read before proceeding When servicing boilerStainless steel heat exchanger Gas connection pipe Knight Wall Mount Boiler How it worksModels 51 Knight Wall Mount Boiler Ahri Rating RatingsBefore locating the boiler, check Installation must comply withCloset and alcove installations Determine boiler location1Closet Installation Minimum Required Clearances Prevent combustion air contamination PrecautionsVent and air piping Wall mounting locationWhen using an existing vent system to install a new boiler Products to avoidAreas likely to have contaminants When removing a boiler from existing common vent system Prepare boiler Remove boiler from wood palletGas conversions Mounting to a metal studded wall Mounting the boilerMounting to a wood studded wall Mounting to a concrete wallGeneral venting Direct venting options Sidewall VentDirect venting options Vertical Vent Air intake/vent connections Install vent and combustion air pipingRequirements for installation in Canada SizingLength Air inlet pipe materials MaterialsOptional room air Air contaminationModel Kit Number Material Standard Vent fittingsPrimer Centrotherm InnoFlue SW PolypropyleneFlue Intake Air Adapter Termination Stainless steel ventApproved Stainless Steel Vent Manufacturers Make Model FlueDetermine location If using the alternate sidewall terminationSidewall direct venting Vent/air termination sidewall2AClearance to Gravity Air Inlets Prepare wall penetrations Alternate Field Supplied Option Prepare wall penetrations5AMultiple Vent Terminations must also comply with -1A Multiple vent/air terminationsSidewall termination installation Sidewall termination optional concentric ventDescription and usage Sidewall termination optional concentric vent models 8Concentric Vent Dimensional DrawingMultiventing sidewall terminations 10Concentric Vent Sidewall AttachmentVent/air termination vertical Vertical direct venting2Vertical Terminations with Multiple Boilers Prepare roof penetrationsVertical termination optional concentric vent Vertical termination installationMinimum Combustion AIR Typical Multiventing vertical terminationsConcentric Venting Arrangement Alternate vertical concentric ventingAIR Inlet Flue Exhaust Seal CAP Existing Flue Outlet Existing vent as a chaseChilled water system Hydronic pipingSystem water piping methods General piping information Low water cutoff deviceNear boiler piping components Circulator sizing Near boiler piping connectionsArmstrong Pump Size GrundfosUP26-96 FC/VS IFC VS Stratos 1.25 3 x Smart System / Multi-temperature loop control optionVariable speed pump setup Variable speed pump option3Single Boiler Single Temperature Zoned with Circulators Number of Units 5Single Boiler Multiple Temperatures Required Pipe Sizes Model 8Single Boiler Zoned with Valves Model Number of Units 10Single Boiler Non-Zoned Primary/Secondary Piping Gas connections Connecting gas supply pipingPropane Gas Natural gasNatural Gas Pipe Capacity Chart Check inlet gas supplyLength of Pipe in Straight Feet for 1/2 PSI Gas Pressure Gas valve replacementLow voltage connections Field wiringInstallation must comply with Line voltage connectionsThermostat Outdoor temperature sensorLouver proving switch Flow switchBoiler management system Alarm contactsWiring of the cascade System supply sensor4Low Voltage Field Wiring Connections Condensate drain Condensate disposalFill and test water system Freeze protection when usedStart-up Check/control water chemistryInspect/check condensate lines and fittings Clean/Inspect Trap AssemblyCheck for gas leaks Check thermostat circuits Inspect/fill condensate systemCheck system and boiler Final checks before starting the boilerStart the boiler If boiler does not start correctly2Operating Instructions Natural Gas Propane Set space heating operationVerify DHW mode Configuration of the cascadeSet domestic hot water DHW operation How the control module operates Operating informationGeneral How the boiler operatesProtection features Temperature controlBoiler temperature regulation Cascade Outdoor reset operation, if usedOperation Display Sequence of operationAccess modes InstallerUser 1Control Panel Knight wall mount boiler control moduleCall for Heat Operating information Dial Function Maintenance Maintenance and annual startup Service technicianOwner maintenance Maintenance Check expansion tank Check ignition ground wiringCheck all boiler wiring Check control settingsCheck flame signal Cleaning boiler heat exchangerReview with owner Oiled bearing circulators Heat Exchanger Cleaning KitsPC Interface Diagrams2Wiring Diagram