Lochinvar 51-211 operation manual Requirements for installation in Canada, Sizing, Length

Page 16

3 General venting

Requirements for installation in Canada

1.Installations must be made with a vent pipe system certified to ULC-S636.

IPEX is an approved vent manufacturer in Canada supplying vent material listed to ULC-S636.

2.The first three (3) feet of plastic vent pipe from the appliance flue outlet must be readily accessible for visual inspection.

3.The components of the certified vent system must not be interchanged with other vent systems or unlisted pipe/fittings.

4.The 2" and 3" Concentric Vent Kits available from Lochinvar (see Section 4 – Sidewall Termination – Optional Concentric Vent) and the 2" and 3" Concentric Vent Kits available from IPEX are approved for use on the Knight wall mount boiler. Both kits are listed to the ULC-S636 standard for use in Canada.

Sizing

The Knight wall mount boiler uses model specific combustion air intake and vent piping sizes as detailed in Table 3A below.

Table 3A Maximum Combustion Air and Vent Piping Lengths

Model

2" Max Vent/Air

3" Max Vent/Air

51

 

40 feet

100 feet

81

 

40 feet

100 feet

106

 

40 feet

100 feet

151

 

N/A

100 feet

211

 

N/A

100 feet

 

 

Increasing or decreasing combustion air or

NOTICE

vent piping sizes is not authorized.

Installation & Operation Manual

Minimum / Maximum allowable combustion air and vent piping lengths are as follows:

Combustion Air = 12 equivalent feet minimum / 100 equivalent feet maximum

Vent = 12 equivalent feet minimum / 100 equivalent feet maximum

When determining equivalent combustion air and vent length, add 5 feet for each 90° elbow and 3 feet for each 45° elbow.

EXAMPLE: 20 feet of PVC pipe + (4) 90° elbows + (2) 45° elbows + (1) concentric vent kit (CVK3003) = 49 equivalent feet of piping.

NOTICE

The appliance output rating will reduce

by up to 1.5% for each 25 feet of vent

 

length.

Table 3B Concentric Vent Kit Equivalent Vent Lengths

Model

Kit Number

Equivalent Vent

 

 

Length

51 - 106

CVK3008

3 feet

 

 

 

51 - 211

CVK3003

3 feet

 

 

 

16

Image 16
Contents Models 51 Contents When servicing boiler Please read before proceedingKnight Wall Mount Boiler How it works Stainless steel heat exchanger Gas connection pipeModels 51 Ratings Knight Wall Mount Boiler Ahri RatingInstallation must comply with Closet and alcove installationsDetermine boiler location Before locating the boiler, check1Closet Installation Minimum Required Clearances Precautions Vent and air pipingWall mounting location Prevent combustion air contaminationProducts to avoid When using an existing vent system to install a new boilerAreas likely to have contaminants When removing a boiler from existing common vent system Remove boiler from wood pallet Prepare boilerGas conversions Mounting the boiler Mounting to a wood studded wallMounting to a concrete wall Mounting to a metal studded wallDirect venting options Sidewall Vent General ventingDirect venting options Vertical Vent Install vent and combustion air piping Air intake/vent connectionsSizing Requirements for installation in CanadaLength Materials Air inlet pipe materialsAir contamination Optional room airModel Kit Number Vent fittings Material StandardPrimer Polypropylene Centrotherm InnoFlue SWStainless steel vent Approved Stainless Steel Vent Manufacturers Make ModelFlue Flue Intake Air Adapter TerminationIf using the alternate sidewall termination Sidewall direct ventingVent/air termination sidewall Determine location2AClearance to Gravity Air Inlets Prepare wall penetrations Prepare wall penetrations Alternate Field Supplied OptionMultiple vent/air terminations 5AMultiple Vent Terminations must also comply with -1ASidewall termination optional concentric vent Sidewall termination installationDescription and usage 8Concentric Vent Dimensional Drawing Sidewall termination optional concentric vent models10Concentric Vent Sidewall Attachment Multiventing sidewall terminationsVertical direct venting Vent/air termination verticalPrepare roof penetrations 2Vertical Terminations with Multiple BoilersVertical termination installation Vertical termination optional concentric ventMultiventing vertical terminations Minimum Combustion AIR TypicalAlternate vertical concentric venting Concentric Venting ArrangementExisting vent as a chase AIR Inlet Flue Exhaust Seal CAP Existing Flue OutletHydronic piping System water piping methods General piping informationLow water cutoff device Chilled water systemNear boiler piping components Near boiler piping connections Circulator sizingPump Size Grundfos ArmstrongSmart System / Multi-temperature loop control option Variable speed pump setupVariable speed pump option UP26-96 FC/VS IFC VS Stratos 1.25 3 x3Single Boiler Single Temperature Zoned with Circulators Number of Units 5Single Boiler Multiple Temperatures Required Pipe Sizes Model 8Single Boiler Zoned with Valves Model Number of Units 10Single Boiler Non-Zoned Primary/Secondary Piping Connecting gas supply piping Gas connectionsNatural gas Propane GasCheck inlet gas supply Natural Gas Pipe Capacity ChartLength of Pipe in Straight Feet for 1/2 PSI Gas valve replacement Gas PressureField wiring Installation must comply withLine voltage connections Low voltage connectionsOutdoor temperature sensor Louver proving switchFlow switch ThermostatAlarm contacts Wiring of the cascadeSystem supply sensor Boiler management system4Low Voltage Field Wiring Connections Condensate disposal Condensate drainFreeze protection when used Start-upCheck/control water chemistry Fill and test water systemClean/Inspect Trap Assembly Check for gas leaks Check thermostat circuitsInspect/fill condensate system Inspect/check condensate lines and fittingsFinal checks before starting the boiler Start the boilerIf boiler does not start correctly Check system and boiler2Operating Instructions Set space heating operation Natural Gas PropaneConfiguration of the cascade Verify DHW modeSet domestic hot water DHW operation Operating information GeneralHow the boiler operates How the control module operatesTemperature control Protection featuresBoiler temperature regulation Outdoor reset operation, if used CascadeSequence of operation Operation DisplayInstaller Access modesUser Knight wall mount boiler control module 1Control PanelCall for Heat Operating information Dial Function Service technician Maintenance Maintenance and annual startupOwner maintenance Maintenance Check ignition ground wiring Check all boiler wiringCheck control settings Check expansion tankCleaning boiler heat exchanger Check flame signalReview with owner Heat Exchanger Cleaning Kits Oiled bearing circulatorsDiagrams PC Interface2Wiring Diagram
Related manuals
Manual 16 pages 37.78 Kb